Seaside, OR Building Safety: Building Inspections (2026)
Key Facts
- Who requests inspections
- The permit holder or authorized agent (§ 150.72(A))
- Before permitted work starts
- Inspection record card posted or made available (§ 150.72(B))
- Work must stay
- Accessible and exposed for inspection
- Permit holder supplies
- Site access and equipment the Building Official deems necessary
- Final inspection deadline
- Within 24 months of the permit date (§ 150.02(B)(1))
- Entry to inspect
- Building Official, at reasonable times (§ 150.63)
- Fine ceiling
- $1,000 on conviction (§ 150.99(A))
Summary
In Seaside the permit holder or authorized agent must request every necessary or required inspection in a timely manner, provide access to the site and supply the equipment the Building Official deems necessary. Construction does not proceed until the Building Official authorizes it, and an inspection record card must be posted before permitted work starts.
(A) It shall be the duty of the permit holder or ... authorized agent to request all inspections that may be ... necessary or otherwise required in a timely manner, ... provide access to the site, and to provide all ... equipment as may be deemed necessary or appropriate by the Building Official. The permit holder shall not ... proceed with construction activity until authorized to ... do so by the Building Official. It shall be the duty of ... the permit holder to cause the work to remain accessible and exposed for inspection purposes. Any ... (B) Work requiring a permit shall not be ... commenced until the permit holder or an agent of the ... permit holder has posted or otherwise made available ... an inspection record card such as to allow the Building ... Department to conveniently make the required entries regarding inspection of the work.
Full Breakdown
Section 150.72 puts the burden of the inspection process on the permit holder. Under paragraph (A), the permit holder or authorized agent must request all inspections that are necessary or otherwise required, in a timely manner, provide access to the site, and supply all equipment the Building Official deems necessary or appropriate. The permit holder shall not proceed with construction activity until authorized to do so by the Building Official, and it is the holder's duty to keep the work accessible and exposed for inspection. Any expense of removing or replacing material required for proper inspection is the responsibility of the permit holder or the holder's agent.
Paragraph (B) adds the paperwork. Work requiring a permit cannot be commenced until the permit holder or an agent has posted or otherwise made available an inspection record card, so the Building Department can conveniently enter the required inspection results. The card stays available until the Building Department grants final approval. Final approval has a deadline, because under § 150.02(B)(1) a permit for work that is not completed and given a final inspection within 24 months of the permit date expires and becomes null and void.
The Building Official's other tools surround the inspection. Section 150.63 authorizes entry at reasonable times to inspect when that is necessary to enforce the subchapter or when there is reasonable cause to believe a condition violates it. At an occupied building, credentials are presented to the occupant and entry is requested. At an unoccupied one, the Building Department first makes a reasonable effort to locate the owner or other person in charge. If entry is refused, the Building Official has recourse to the remedies provided by O.R.S. to secure entry. Section 150.60 lets the Building Official require tests as proof of compliance, made at no expense to the jurisdiction by an approved testing agency. Section 150.64 authorizes written stop work orders. A decision on alternate materials and methods, or an interpretation by the Building Official, goes to the Board of Appeals, and the appeal is in writing and is first filed with the Building Department (§ 150.69).
Violations & Fines
Section 150.72 carries the notation Penalty, see § 150.99. A Chapter 150 violation with no specific penalty is punished on conviction in municipal court by a fine not to exceed $1,000, and a violating condition is also a public nuisance the city can abate (§ 150.99(A), (C)). Proceeding with work contrary to the subchapter can draw a written stop work order that holds everyone engaged in the work until the Building Official specifically authorizes them to proceed (§ 150.64).
Frequently Asked Questions
Who has to call for inspections in Seaside?
What is the inspection record card in Seaside?
Who pays to uncover work that was covered before inspection?
Can the Building Official enter my property to inspect?
How long do I have to get a final inspection?
Sources & Official References
Other rules in Seaside
Compare Seaside to another location·View the Oregon building safety overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.