Skip to main content
CityRuleLookup

Stratford, CT Building Safety: Building Inspections (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified October 2026

Key Facts

Certificate of occupancy
Issued by the Building Inspector after zoning compliance
Zoning compliance
Issued by the Office of Planning and Zoning
As-built survey
Licensed surveyor, filed when the foundation is complete
Interim height check
After roof sheathing, before other roofing materials
New construction permit fee
$25 for the first $1,000, then $12 per additional $1,000
Stop order fine
$25 to $500, each day a separate offense

Summary

In the Town of Stratford, Connecticut, the Building Inspector cannot issue a certificate of occupancy until the Office of Planning and Zoning has issued a certificate of zoning compliance. Regulated activities are inspected by staff if necessary, and an as-built survey can be required once a foundation is complete.

D) Certificate of occupancy. No certificate of occupancy shall be issued by the Building Inspector unless a certificate of zoning compliance has been issued by the Office of Planning and Zoning stating that such building and lot as erected or altered, and the use thereof are in conformity with these Regulations. No new, altered, moved, or rebuilt structure shall be occupied for any use except in conformance with these Regulations and after a certificate of occupancy shall have been issued by the Building Inspector as provided in Section 206 of the Building Code. ... E) Certificate of zoning compliance. No certificate of zoning compliance shall be issued by the Office of Planning and Zoning until it has been determined that the said lot(s), building(s), use(s) are developed in conformity with these Regulations. All regulated activities on the site shall require an application for certificate of zoning compliance, be inspected by staff if necessary, and approved prior to the issuance of a certificate of occupancy.

Full Breakdown

Stratford's inspection sequence is built into Section 7.3.2 of the Zoning Regulations. Under item D, no certificate of occupancy is issued by the Building Inspector unless the Office of Planning and Zoning has issued a certificate of zoning compliance stating that the building, lot and use, as erected or altered, conform to the Regulations. No new, altered, moved or rebuilt structure can be occupied until the Building Inspector issues a certificate of occupancy as provided in Section 206 of the Building Code. Item E bars the certificate of zoning compliance until the lot, building and use are developed in conformity with the Regulations, and every regulated activity on the site needs an application for that certificate, is inspected by staff if necessary, and is approved before the certificate of occupancy issues.

Item C(iii) adds the as-built stage. A plan prepared by a licensed land surveyor is required for new construction or expansion of a building footprint unless the Zoning Enforcement Officer identifies clear compliance. It is filed with the Zoning Enforcement Officer upon completion of the foundation. The Officer can also request an interim as-built survey to verify height, measured after the roof sheathing but before other roofing materials, when the applicant builds to or near the maximum height. A building exceeding the maximum height on the final as-built does not get a hardship finding. Item C(i) states that a building permit is no guarantee by the municipality that the structure conforms to the Regulations.

Section 7.4 authorizes the Planning and Zoning Administrator or designee to cause any building, sign, structure, place or premises to be inspected and examined and to order the remedying of any violation in writing.

Chapter 62 sets the permit side. Section 62-1 charges $25 for the first $1,000 and $12 for each additional $1,000 or fraction thereof of estimated cost for new construction, alterations or additions. Section 62-3 requires at least one smoke detector, in a location approved by the Fire Chief, before a certificate of occupancy for a single-family dwelling. Section 62-4 withholds building permits while delinquent real property taxes are owed.

Violations & Fines

Under Section 62-1, anyone who engages in an act covered by the fee schedule without the proper permits pays a penalty equal to double the normal permit fee plus $50. Section 62-2 makes violating the Connecticut State Building Code a misdemeanor punishable by a fine of not more than $500 or imprisonment not exceeding one year, or both, and continuing work after a stop order carries a fine of not less than $25 nor more than $500, with each day a separate offense.

Frequently Asked Questions

What is needed before the Building Inspector issues a certificate of occupancy in Stratford?
Section 7.3.2 item D requires a certificate of zoning compliance from the Office of Planning and Zoning first, stating that the building and lot as erected or altered, and the use, conform to the Regulations. No new, altered, moved or rebuilt structure can be occupied until the certificate of occupancy issues.
When does Stratford require an as-built survey?
An as-built plan is required for any new construction or expansion of a building footprint unless the Zoning Enforcement Officer identifies clear compliance. A licensed land surveyor prepares it, and the permit holder files it with the Zoning Enforcement Officer upon completion of the foundation. The Officer can require one in other situations near setback lines, lot lines or wetland boundaries.
Can the Town check building height during construction?
Yes. The Zoning Enforcement Officer can request an interim as-built survey when the applicant proposes to build to or near the maximum height allowed. The height is measured after the roof sheathing and before other roofing materials are applied. If the final survey shows the structure exceeds the maximum height, that does not constitute a hardship.
What happens if I build in Stratford without a permit?
Section 62-1 imposes a penalty equal to double the normal permit fee plus $50 on anyone who engages in a covered act without the proper permits. Section 62-2 also makes continuing work after a stop order punishable by a fine of not less than $25 nor more than $500, with each day a separate offense.

Sources & Official References

Other rules in Stratford

All Stratford rules

Compare Stratford to another location·View the Connecticut building safety overview

Get notified when Building Inspections in Stratford, CT changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.