Key Facts

Governing code
2018 International Plumbing Code, as amended
Applies in
Unincorporated county + non-adopting municipalities
Permit application
Signed by licensed Master Plumber
Unpermitted work penalty
Double permit fee (Sec. 105.4)
Permit posting
Displayed on-site until final inspection
Sewer tie-ins
Impact Connection fee to Environmental Services

Summary

Jefferson County enforces its own Plumbing Code, adopted from the 2018 International Plumbing Code, in the unincorporated county and in any municipality that hasn't adopted its own plumbing code. A permit from the Building Official is required before connecting sewers, septic systems, or fixtures, or altering existing plumbing.

City-specific rules exist: Birmingham, Hoover, and Vestavia Hills have their own plumbing permits rules that differ from Jefferson County's county-level regulations. If you live in one of those cities, check the city-specific page instead.

104.1.1. General - Any person, firm or corporation who desires to connect any plumbing work with any sewers, sanitary or storm, septic tanks or sewage disposal of any kind, or private connection or install fixtures or appliances in new or existing systems, structures or premises, or repair, or add to any existing plumbing which is regulated by this Code, shall first make application to the Building Official and obtain the required permit for the work. 101.3.1. Applicability - The provisions of this Code shall apply in all unincorporated areas of Jefferson County and also in those parts of said county lying within the corporate limits of municipalities which have not adopted and are not enforcing municipal plumbing Codes.

Full Breakdown

1 fixes its reach: it applies in all unincorporated areas of Jefferson County and also inside any municipality that has not adopted and is not enforcing its own municipal plumbing code. 1 requires anyone who wants to connect plumbing work to a sewer (sanitary or storm), septic tank, or sewage disposal system, or to install, repair, or add to fixtures and appliances in new or existing systems, to first apply to the Building Official and obtain a permit before starting work. 1 also requires paying an Impact Connection fee to the Jefferson County Environmental Services Department, and applying for a Grease Control Permit with Jefferson County Grease Control if applicable, before the plumbing permit is issued.

2 for 500-employee manufacturing companies using a licensed engineer) and makes it unlawful to proceed with plumbing installation or repair before the permit is issued, except under the emergency-permit provision. 7 further requires the issued Plumbing Permit to be posted in a conspicuous place on the front of the premises (or kept in a weatherproof permit/doc box no larger than 36 inches in any dimension) until final inspection. 1, which requires payment to the County before any permit is granted.

Violations & Fines

Starting plumbing work without the required permit triggers Section 105.4: the person doing the unpermitted work must still obtain a permit and pay the required fees at double the normal rate, and any repeat violation or Stop Work Order within twelve months of the last one is also double-fee. If a proper inspection can't be completed on unpermitted work, the Building Official can require it to be uncovered or re-installed so it can be inspected. The Building Official may also suspend or revoke a permit issued in error or on incorrect information under Section 105.2.4.

Frequently Asked Questions

Do I need a permit to do my own plumbing in Jefferson County?
Section 101.6 lets a homeowner install or maintain plumbing on their own property if they do the work themselves for their own or their family's exclusive use, but this doesn't excuse them from the Code's other requirements, including obtaining any required permit for the work performed.
Who can sign a Jefferson County plumbing permit application?
Section 104.2 requires the application to bear the signature of the applicant's authorized Master Plumber, except for the limited 500-employee-company procedure in Section 104.1.2, which instead requires a registered, licensed engineer to sign and certify the completed work.
What happens if I start plumbing work before getting a permit?
Section 105.4 requires you to still obtain the permit and pay all required fees at double the normal rate. Repeat violations or Stop Work Orders within a 12-month period are also charged double, and work that can't be properly inspected may need to be re-exposed or re-installed.
Does the county plumbing code apply inside Birmingham?
No. Section 101.3.1 limits the code to unincorporated Jefferson County and to any municipality that has not adopted and is not enforcing its own municipal plumbing code; Birmingham and other incorporated cities enforce their own adopted plumbing codes instead.

Sources & Official References

Other rules in Jefferson County

All Jefferson County rules

Compare Jefferson County to another location·View the Alabama building safety overview

Get notified when Plumbing Permits in Jefferson County, AL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Plumbing Permits in Cities Across Jefferson County