Key Facts

Permit required
Before any plumbing install, repair, or replace
Governing section
Code of General Ordinances § 9.06(A)
Adopted plumbing code
Wis. Admin. Code SPS 380-387
Licensing
State plumber license under Wis. Stat. ch. 145
Permit expires
Void if work not started in 60 days
Completion window
6 months for plumbing work
Late fee
$100 fee on unpaid permits

Summary

Kenosha requires a permit before installing, altering, or replacing any plumbing system, issued by the Department of City Inspections under Code of General Ordinances Section 9.06. The City has adopted Wisconsin Administrative Code SPS 380-387 as its plumbing code, and only a state-licensed plumber under Wis. Stat. ch. 145 may apply for or perform the permitted work.

A.Permit Required. Any owner, authorized agent or contractor who intends to construct, enlarge, Alter, repair, renovate, move, demolish, or change the Occupancy of a Building, or to erect, install, enlarge, repair, renovate, remove, convert or replace any electrical, gas, mechanical or plumbing system, which is regulated by this Code, or to cause any such Work to be done, shall make application to the Code Official and obtain the required Permit prior to commencing any Work.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 11 Update 1 | Zoning Ordinance: Supplement 9).

Full Breakdown

Section 9.03.C adopts Wisconsin Administrative Code SPS 380-387, Plumbing and Appendices, as part of Chapter IX, the City's Building Code, alongside the other trade codes and statutes on file with the Department of City Inspections. Section 9.06.A then requires a permit before anyone erects, installs, enlarges, repairs, renovates, removes, converts, or replaces any plumbing system regulated by the Code: the owner, authorized agent, or contractor must apply to the Code Official and obtain the permit before starting work.

Section 9.19, Plumbing Qualifications, bars anyone from engaging in plumbing work, or applying for a plumbing permit, without first holding the license, certification, or registration Wis. Stat. ch. 145 requires, covering Master Plumbers, Journeyman Plumbers, Plumbing Apprentices, and Automatic Fire Sprinkler contractors. The Common Council sets permit fees by resolution under Section 9.07. A plumbing permit becomes void if work has not started within sixty days of issuance, and Section 9.06.F gives electric, plumbing, and HVAC work six months to reach completion once started. If permit fees go unpaid after a second billing notice, Section 9.06.E adds a one-hundred-dollar administrative fee and turns the balance into a special charge lien against the property.

Not every plumbing task needs a permit: Section 9.06.H.4 exempts stopping leaks in drain, water, soil, waste, or vent pipes, and clearing stoppages or repairing leaks in pipes, valves, or fixtures, so long as the work does not require replacing or rearranging valves, pipes, or fixtures. Appeals of a Code Official's interpretation of the State Plumbing Code go to the Wisconsin Department of Safety and Professional Services under Section 9.29.A, on the state's own forms.

Violations & Fines

Doing plumbing work without the required permit, or without a Wisconsin plumbing license under Chapter 145, violates Chapter IX. Section 9.30.F sets the citywide building-code penalty: a forfeiture of not less than $25 and not more than $500 per day, plus the costs of prosecution, and up to six months in the County Jail if the forfeiture goes unpaid. Each day of violation counts as a separate offense.

Frequently Asked Questions

Does Kenosha require a permit for plumbing work?
Yes. Code of General Ordinances Section 9.06.A requires anyone who installs, alters, repairs, or replaces a plumbing system to apply to the Department of City Inspections' Code Official and obtain a permit before starting work. Only minor repairs like stopping a leak or clearing a stoppage are exempt under Section 9.06.H.4.
What plumbing code does Kenosha use?
Section 9.03.C adopts Wisconsin Administrative Code SPS 380-387, Plumbing and Appendices, as part of the City's Building Code. Section 32.01 of the Code separately confirms that chapter does not supersede the State of Wisconsin Plumbing Code or the City of Kenosha Plumbing Code, but works alongside them.
Who can pull a plumbing permit in Kenosha?
Section 9.19 bars anyone from engaging in plumbing work or applying for a plumbing permit without holding the license, certification, or registration required under Wisconsin Statutes Chapter 145, covering Master Plumbers, Journeyman Plumbers, and Plumbing Apprentices.
How long is a Kenosha plumbing permit good for?
The permit becomes void if construction has not commenced within sixty days of issuance. Once plumbing work begins, Section 9.06.F gives the contractor six months to complete it before running afoul of the Code.

Sources & Official References

Other rules in Kenosha

All Kenosha rules

Compare Kenosha to another location·View the Wisconsin building safety overview

Get notified when Plumbing Permits in Kenosha, WI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.