Environmental Rules in Dothan, AL (2026)
4 verified environmental rules for Dothan, Alabama, sourced directly from the municipal code and official government pages.
Verified from official government sources
Stormwater Management
In the City of Dothan, Alabama, City Code § 83-3 bars illicit discharges of pollutants, industrial stormwater without an NPDES permit, and any spilling or dumping of non-stormwater material into the city's municipal separate storm sewer system (MS4). The public works director enforces the article, and § 83-17 makes a conviction punishable under Ala. Code § 11-45-9 as adopted by Chapter 1.
Dothan Stormwater Discharge Prohibitions
Significant RestrictionsDothan City Code §§ 83-3, 83-17
(a)The illicit discharge of pollutants to the MS4 is prohibited.(b)The discharge of pollutants to the MS4 by discharging stormwater associated with industrial activity is prohibited except as authorized by a NPDES permit. ... (c)The spilling, dumping, or disposal of materials other than stormwater to the MS4 is prohibited. ... Any person who violates any provision of this article or any provisi...
Erosion Control
In the City of Dothan, Alabama, City Code § 83-22 requires a city permit before any land-disturbing construction activity of one acre or more, or any non-residential project regardless of size. Applicants may have to post a bond of up to $5,000.00 per acre, and § 83-26 bars clearing land until erosion and sediment controls required by the approved BMP plan are installed and stabilized.
Dothan Construction Erosion Control Permits
Significant RestrictionsDothan City Code §§ 83-22, 83-26
(a)No land disturbing activities for non-residential development, regardless of size, or that disturb either (i) greater than or equal to one acre; or (ii) less than one acre but whose activity is part of a larger common plan of development or sale that disturbs one acre or more ... shall be conducted within the city without first obtaining the necessary permit(s) from the city. ... (d)The city...
Flood Zones
In the City of Dothan, Chapter 42 of the Code of Ordinances regulates every FEMA-designated special flood hazard area and any other area the city designates as flood-prone. Sec. 42-68 requires a floodplain development permit before any construction, filling, grading or similar development begins in those areas, based on FIRMs from the May 2, 2016 flood insurance study.
Dothan Floodplain Development Permit Requirements
Some RestrictionsDothan City Code §§ 42-31, 42-33, 42-68
Sec. 42-31. - Lands to which article applies. This article shall apply to all FEMA SFHAs and any additional areas designated by the city as floodplains or areas subject to flooding within the jurisdiction of the city. ... ... Sec. 42-33. - Basis for special flood hazard areas. The SFHAs identified by the Federal Emergency Management Agency in its flood insurance study (FIS), dated May 2, 2016, ...
Flood Elevation Requirements
In the City of Dothan, Sec. 42-97(a) of the Code of Ordinances sets the base flood elevation standard: where BFE data exists, new construction and substantial improvements must have their lowest floor, including any basement, elevated at least one foot above the base flood elevation, the freeboard margin the code requires citywide.
Dothan Requires One Foot of Flood Freeboard
Some RestrictionsDothan City Code §§ 42-26, 42-97(a)
Base flood elevation means the elevation of surface water resulting from a flood that has a one percent chance of equaling or exceeding that level in any given year. ... Freeboard means a factor of safety usually expressed in feet above a flood level for purposes of flood plain management. ... ... Sec. 42-97. - Specific technical standards. ... (a)Residential and nonresidential structures. Wher...