Data Center Zoning & Siting
El Monte has no data-center ordinance and no "data center" use category. Data centers locate in the M-1 (Light Manufacturing) or M-2 (General Manufacturing) zones, classified into the closest listed use - light manufacturing, research and development, or office - under the 2025 Zoning Code, Table 17.42-1.
El Monte Data Center Zoning and Siting
Some RestrictionsEl Monte, CA, Zoning Code (Title 17) Sec. 17.42.010 (Manufacturing Zoning Districts - M-1 Light Manufacturing); Table 17.42-1 (Permitted Uses)
This zoning district is principally established to provide areas appropriate for a diverse range of light industrial uses, including limited manufacturing and processing, research and development, fabrication, utility equipment and service yards, wholesaling, warehousing, and distribution activities. Other uses such as office, retail and restaurants are also permitted.
Data Center Noise Limits
El Monte caps property-line noise by zone under Municipal Code Chapter 8.36: 50 dBA day and 45 dBA night at single-family homes, 65/60 commercial, and 70 dBA in industrial zones. A data center's fixed cooling and generator noise cannot exceed these ambient limits by more than 5 dBA.
El Monte Data Center Noise Limits
Some RestrictionsEl Monte, CA, Municipal Code Sec. 8.36.040 (Ambient Noise Standards); Chapter 8.36 (Noise Control)
It is unlawful for any person to create any noise which would cause the noise level at the property line of any property to exceed the ambient noise level by more than five (5) decibels for a cumulation period of fifteen (15) minutes in any hour.