Key Facts

Dedicated ordinance
None
Zones
M-1, M-2 manufacturing
By-right
Light manufacturing, R&D, office
CUP trigger
New build near homes / 100k sf
Discretionary review
CEQA + hearing

Summary

El Monte has no data-center ordinance and no "data center" use category. Data centers locate in the M-1 (Light Manufacturing) or M-2 (General Manufacturing) zones, classified into the closest listed use - light manufacturing, research and development, or office - under the 2025 Zoning Code, Table 17.42-1.

This zoning district is principally established to provide areas appropriate for a diverse range of light industrial uses, including limited manufacturing and processing, research and development, fabrication, utility equipment and service yards, wholesaling, warehousing, and distribution activities. Other uses such as office, retail and restaurants are also permitted.

Source: El Monte Zoning Code (Title 17, Ch. 17.42) & Municipal Code Chapter 8.36 Noise ControlView official code

Full Breakdown

El Monte's 2025 Zoning Code (Title 17, Chapter 17.42) names no "data center" use. Any use not listed in Table 17.42-1 is barred unless the Planning Director classifies it into an analogous use under Section 17.12.050. A server building operating as light manufacturing, research and development, or an office is permitted by-right with a ministerial building permit. New industrial construction over 5,000 square feet within 150 feet of a residential zone requires a Conditional Use Permit; a distribution or warehouse center of 100,000 square feet or more also needs a CUP. A CUP is discretionary, triggering CEQA review and a Planning Commission hearing. El Monte has adopted no moratorium.

Violations & Fines

Building or operating a data center outside the M-1 or M-2 zones, or without a required Conditional Use Permit, is a zoning violation enforced by El Monte Community Development through stop-work orders, penalties, and abatement.

Frequently Asked Questions

Where can data centers be built in El Monte?
In the M-1 and M-2 manufacturing zones under Chapter 17.42. There is no data-center use category, so the Planning Director classifies each project into the closest listed use in Table 17.42-1.
Does El Monte require a special permit for a data center?
Not always. A facility operating as light manufacturing, R&D, or office is by-right. New construction over 5,000 square feet within 150 feet of homes needs a Conditional Use Permit and CEQA review.
Has El Monte passed a data-center ordinance?
No. El Monte has no data-center ordinance or moratorium. Residents wanting tailored standards can petition the Planning Commission or City Council through the Planning Division at ci.el-monte.ca.us/262/Planning.

Sources & Official References

Other rules in El Monte

All El Monte rules

California rules heatmap·Compare El Monte to another location·View the California data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in El Monte, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Data Center Zoning & Siting in Nearby Cities

How other cities in Los Angeles County handle data center zoning & siting.

Long Beach, CA
Light Restrictions
Los Angeles, CA
Some Restrictions
Pasadena, CA
Some Restrictions
Torrance, CA
Some Restrictions
Palmdale, CA
Some Restrictions
Lakewood, CA
Some Restrictions
Norwalk, CA
Some Restrictions
Glendale, CA
Some Restrictions