Stormwater Management

Every development in Gainesville must treat the first inch of stormwater runoff on-site and control stormwater quantity for a 100-year critical duration storm, so post-development peak flow off the site never exceeds the natural predevelopment flow, under Section 30-6.13.B.1 of the Land Development Code.

Gainesville Stormwater Management Design Standards

Some Restrictions

Gainesville Land Development Code § 30-6.13(B)(1)(a)

iii.All basins designed to be dry shall drain completely within 72 hours of the storm event. Designs providing for longer drainage periods require approval by the city manager or designee.iv.All development shall provide on-site stormwater quality treatment for the first one inch of stormwater runoff, except as provided in subsection e. of this section. ... v.All development shall have on-site ...

Erosion Control

Gainesville can require developers to limit clearing and grubbing, control erosion and sedimentation during and after construction, stabilize cleared areas, and protect stormwater inlets, under Section 30-6.13.B.1.b of the Land Development Code. Mud or debris tracked onto a paved public road must be removed by the end of each day.

Gainesville Construction Erosion and Sediment Control

Some Restrictions

Gainesville Land Development Code § 30-6.13(B)(1)(b)

b.Erosion and sedimentation control. The city may require the developer to limit clearing and grubbing outside the proposed developed area to the site, control erosion and sedimentation during and after construction, stabilize cleared areas, limit stockpiles, protect stormwater inlets during construction, control construction access routes, remove temporary control systems after construction, a...

Flood Zones

Any development wholly or partly inside a mapped flood hazard area in Gainesville needs a floodplain development permit or approval from the city's floodplain administrator before work begins, on top of any building permit, under the city's Floodplain Management Ordinance.

Floodplain Development Permit Rules in Gainesville

Some Restrictions

Gainesville Land Development Code § 30-8.27(A)

A.Permits required. Any owner or authorized agent who intends to undertake any development within the scope of FPO Division 5, including buildings, structures and facilities exempt from the Florida Building Code, which is wholly or partially within any flood hazard area shall first apply to the floodplain administrator, and the building official if applicable, and shall obtain the required perm...

Flood Elevation Requirements

New buildings and substantial improvements inside a Gainesville flood hazard area must have their lowest finished floor set at least 2.0 feet above the base flood elevation, whether the structure is residential or non-residential, under the city's floodplain ordinance.

Base Flood Elevation Freeboard Rules in Gainesville

Some Restrictions

Gainesville Land Development Code § 30-8.32(B)-(C)

B.Elevation requirements for residential structures (as defined by ASCE 24). All new structures and substantial improvements of structures within the flood hazard area shall have the lowest finished floor elevated at a minimum elevation of 2.0 feet above the base flood elevation.C.Elevation requirements for non-residential structures (as defined by ASCE 24). All new structures and substantial i...