Key Facts

Water quality treatment
First 1 inch of runoff, on-site
Quantity control design storm
100-year critical duration storm
Dry basin drawdown
72 hours after storm event
Fill slope limit
No steeper than 3:1
Hogtown Creek Basin
72-hour volume retention, stricter standard

Summary

Every development in Gainesville must treat the first inch of stormwater runoff on-site and control stormwater quantity for a 100-year critical duration storm, so post-development peak flow off the site never exceeds the natural predevelopment flow, under Section 30-6.13.B.1 of the Land Development Code.

iii.All basins designed to be dry shall drain completely within 72 hours of the storm event. Designs providing for longer drainage periods require approval by the city manager or designee.iv.All development shall provide on-site stormwater quality treatment for the first one inch of stormwater runoff, except as provided in subsection e. of this section. ... v.All development shall have on-site stormwater quantity control designed for the 100-year critical duration storm, except as provided otherwise in this section. A detention system shall be provided that will permit a controlled outlet to receiving watercourses. The system shall be designed so that the peak flow of stormwater off of the site, assuming full development, shall not exceed the natural flow from the lands prior to the subdivision or any development, based on the 100-year critical duration storm.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 63).

Full Breakdown

Section 30-6.13 of the Gainesville Land Development Code opens with a prohibition: no one may change the contour, topography, use or vegetation cover of land unless the resulting stormwater runoff and sedimentation are controlled under this article, with narrow exceptions for active agriculture (excluding silviculture), home gardening and routine landscape maintenance, and permitted tree removal. No one may discharge stormwater runoff or sedimentation into creeks, watercourses or water bodies without the applicable governmental authority's consent.

Subsection B.1 sets the design standards. Every drainage facility needs a positive outfall to an existing watercourse, water body, wetland or storm sewer system unless it is proven to be a closed system, and the property owner remains fully responsible for compliance with county, water management district, state Department of Environmental Protection, U.S. Army Corps of Engineers and EPA rules. Dry basins must drain completely within 72 hours of a storm event unless the city manager or designee approves a longer period. All development must provide on-site stormwater quality treatment for the first inch of runoff, and on-site stormwater quantity control designed for the 100-year critical duration storm, with a detention system whose controlled outlet keeps the post-development peak flow off the site from exceeding the natural predevelopment flow. Fill slopes for purposes other than landscaping or buffering cannot be steeper than three-to-one and must be stabilized by vegetation or another approved method, and excessive erosion of any cut or fill slope requires remediation by the property owner. Within the Hogtown Creek Basin, systems must retain any increase in runoff volume above the predevelopment volume for a 72-hour period, a stricter local standard layered on top of the citywide rule.

Violations & Fines

Grading or clearing land without controlling the resulting runoff and sedimentation, discharging stormwater into a creek or water body without authorization, or building a detention system that lets post-development peak flow exceed the natural predevelopment flow all violate Section 30-6.13's prohibitions and design standards, and can trigger a stop-work order, required remediation of eroded slopes, or denial of a certificate of occupancy until the site meets the article's requirements.

Frequently Asked Questions

Does Gainesville require on-site stormwater treatment for new development?
Yes. Section 30-6.13.B.1.a.iv requires all development to provide on-site stormwater quality treatment for the first inch of runoff, and Section 30-6.13.B.1.a.v requires on-site quantity control designed for the 100-year critical duration storm so post-development peak flow does not exceed the natural predevelopment flow.
Who is responsible for stormwater facility compliance in Gainesville?
The property owner. Section 30-6.13.B.1.a.ii states the property owner is fully responsible for compliance with all county, water management district, state Department of Environmental Protection, U.S. Army Corps of Engineers and EPA rules governing the site's drainage facilities.
Are there stricter stormwater rules near Hogtown Creek in Gainesville?
Yes. Section 30-6.13.B.1.c requires systems within the Hogtown Creek Basin to retain any increase in runoff volume over the predevelopment volume for a full 72-hour period, a tighter standard than the citywide detention rules in the rest of Section 30-6.13.

Sources & Official References

Other rules in Gainesville

All Gainesville rules

Florida rules heatmap·Compare Gainesville to another location·View the Florida environmental rules overview

Get notified when Stormwater Management in Gainesville, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.