Environmental Rules in Skowhegan, ME (2026)
5 verified environmental rules for Skowhegan, Maine, sourced directly from the municipal code and official government pages.
Verified from official government sources
Stormwater Management
In the Town of Skowhegan, Maine, a non-residential project that needs site plan review must file a Stormwater Management Plan, and runoff leaving the site after development cannot exceed the predevelopment rate unless it discharges directly to the Kennebec River. Separate road standards govern storm drains in Town ways.
Skowhegan, Maine Stormwater Management Rules
Some RestrictionsSkowhegan Site Plan Review Ordinance, Section XIV(1)(C) Stormwater Management
C. Stormwater Management: ... Adequate provisions must be made for the collection and disposal of all stormwater that runs off proposed streets, parking areas, roofs, and other surfaces, through a Stormwater Management Plan. To the extent possible, the plan must retain stormwater on the site using the natural features of the site and must not have adverse impacts on abutting or downstream prope...
Erosion Control
In the Town of Skowhegan, Maine, any permitted filling, grading or excavation inside the shoreland zone needs a written soil erosion and sedimentation control plan approved by the permitting authority. Exposed ground must be stabilized within one week of last work, and permanent stabilization is due within nine months.
Skowhegan, ME Shoreland Erosion and Sediment Control Rules
Some RestrictionsSkowhegan Shoreland Zoning Ordinance § 15(P)(1), (4), (5)
1. All activities, which involve filling, grading, excavation, or other similar activities which result in unstabilized soil conditions, and which require a permit shall also require a written soil erosion and sedimentation control plan. The plan shall be submitted to the permitting authority for approval and shall include, where applicable, provisions for: ... 4. Any exposed ground area shall ...
Flood Zones
In the Town of Skowhegan, Maine, any construction or other development inside the FEMA-mapped Zones A and AE needs a Flood Hazard Development Permit from the Planning Board before work begins, in addition to any other Town permit. The application fee is $50.00, paid to the Town Clerk, and the Code Enforcement Officer serves as Floodplain Administrator.
Floodplain Development Permits in Skowhegan, Maine
Significant RestrictionsSkowhegan Floodplain Management Ordinance (enacted June 10, 2024) Art. I, Art. III and Art. V
The areas of special flood hazard, Zones A and AE, for the Town of Skowhegan, Maine, identified by the Federal Emergency Management Agency in a report entitled “Flood Insurance Study — Town of Skowhegan Maine” dated September 20, 1995, with accompanying "Flood Insurance Rate Map" dated September 20, 1995, are hereby adopted by reference and declared to be a part of this Ordinance. ... Before an...
Boat Dock Permits
In the Town of Skowhegan, Maine, a dock, pier or wharf must be no larger than necessary for its activity, and no new structure can be built on one unless it needs direct water access as an operational necessity. Structures on a dock cannot exceed 20 feet in height outside the General Development District. New permanent structures also need a state Department of Environmental Protection permit.
Docks and Piers in Skowhegan, Maine Shoreland Zone
Some RestrictionsSkowhegan Shoreland Zoning Ordinance § 15(C)(4), (5), (7) and NOTE
4. The facility shall be no larger in dimension than necessary to carry on the activity and be consistent with the surrounding character and use, of the area. 5. No new structure shall be built on, over, or abutting a pier, wharf, or other structure extending beyond the normal high-water line of a water body or within a wetland unless the structure requires direct access to the water body or we...
Flood Elevation Requirements
In the Town of Skowhegan, Maine, a new or substantially improved residential structure in Zone AE needs its lowest floor, including the basement, at least one foot above base flood elevation. In Zone A with no base flood data, the floor must be at least two feet above the highest adjacent grade. Utility equipment must also sit one foot above base flood elevation.
Flood Elevation Requirements in Skowhegan, Maine
Significant RestrictionsSkowhegan Floodplain Management Ordinance (enacted June 10, 2024) Art. VII(F) and Art. VII(H)
F. Utilities - New construction or substantial improvement of any structure (including manufactured homes) located within Zones A and AE, shall have the bottom of all electrical, heating, plumbing, ventilation and air conditioning equipment, permanent fixtures and components, HVAC ductwork and duct systems, and any other utility service equipment, facilities, machinery, or connections servicing...