Weld County, CO Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified October 2026

Key Facts

Definition (Section 23-1-90)
Buildings housing IT equipment, with no peak electrical load limit
I-1 Light Industrial
Use by Special Review, Planning Commission and Board hearing
I-2 and I-3
Site Plan Review approved and recorded, no public hearing
Noise cap
65 dB(C) at any point on the property boundary
Backup power
Ancillary systems total under fifty (50) megawatts
Heat limit
No more than 5 degrees Fahrenheit rise at the lot line
Approval deadline
Three years to start construction or use

Summary

Weld County's zoning code names data centers as a use in three industrial districts. In I-1 Light Industrial a data center needs a Use by Special Review permit, which means Planning Commission review and a Board of County Commissioners public hearing. In I-2 Medium Industrial and I-3 Heavy Industrial it needs only an approved, recorded Site Plan Review. A 65 dB(C) boundary noise cap applies to every data center.

These county ordinances apply to unincorporated areas of Weld County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Uses by Special Review. The following BUILDINGS, STRUCTURES and USES may be constructed, occupied, operated and maintained in the I-1 Zone District upon approval of a permit in accordance with the requirements of Article II, Division 4 of this Chapter. ... 6. DATA CENTERS. ... Uses allowed subject to Site Plan Review. The following USES shall be allowed in the I-2 Zone District following approval and recording of a Site Plan in accordance with Article II, Division 3, of this Chapter. Any USE conducted outside of an ENCLOSED BUILDING shall be SCREENED from adjacent PUBLIC RIGHTS-OF-WAY and ADJACENT LOTS in any Zone District other than I-3. ... 10. DATA CENTERS.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Charter and County Code: Supplement 95).

Full Breakdown

Section 23-1-90 defines a DATA CENTER as a building or buildings that house information technology or telecommunications equipment used to process, transfer or store digital information, with no limit on peak electrical load. Offices, security buildings and cooling water tanks count as ancillary structures, and backup power systems fall within the definition only below a total generation capacity of fifty (50) megawatts.

The use lists decide the process. Section 23-3-310(F)(6) makes DATA CENTERS a Use by Special Review in the I-1 (Light Industrial) district. Section 23-3-320(C)(10) allows them in I-2 (Medium Industrial) after Site Plan Review, and Section 23-3-330(C)(13) does the same in I-3 (Heavy Industrial). No other zone district use list in Chapter 23 names data centers. In I-2 and I-3, any use conducted outside an enclosed building must be screened from adjacent public rights-of-way and adjacent lots in any zone district other than I-3.

In I-1 the Planning Commission reviews the Special Review Permit request and forwards a recommendation, then the Board of County Commissioners holds a public hearing under Section 23-2-230. The applicant carries the burden of proof on seven standards, including consistency with Chapter 22, compatibility with existing and future surrounding land uses, and adequate protection of neighborhood and county health, safety and welfare. The Board can attach conditions and require performance guarantees. The permit map must be recorded within 120 days of the Board resolution, and construction or use must begin within three years of approval unless the Board specified otherwise (Section 23-2-290).

In I-2 and I-3, Section 23-2-150 bars any use or development until the Department of Planning Services approves and records the Site Plan Review map, and no building permit issues before that. Section 23-2-175 states that no public hearings are conducted for a Site Plan Review. Construction must begin within three years of approval, or the approval terminates 30 days after notice (Section 23-2-170).

Sections 23-2-160(U)(1) and 23-2-250(A) add a data-center-only limit on top of the dB(A) limits in Section 14-9-40: no data center can exceed 65 dB(C) at any point on the subject property boundary. The same standards cap heat at a 5 degree Fahrenheit rise in air temperature at the lot line, require shielded lighting, and limit grass and weeds to 12 inches.

Violations & Fines

Operating a data center in I-2 or I-3 without an approved Site Plan Review is a violation, enforced through the procedures in Article X of Chapter 23 (Section 23-2-180). If an approved plan is not followed, the Director of Planning Services sends written notice of the deficiencies, and continued refusal to comply can end the approval by first-class mail notice. The owner can appeal under Section 2-4-10. A special review permit ends after three consecutive years of discontinued use, and a contested vacation goes to a Board hearing on at least ten days' notice.

Frequently Asked Questions

Does a data center need a public hearing in Weld County?
In the I-1 district, yes. A Use by Special Review goes to the Planning Commission and then to a Board of County Commissioners public hearing. In I-2 and I-3, no. Section 23-2-175 states that no public hearings are conducted for a Site Plan Review, and the Board has delegated that approval to the Department of Planning Services under Section 23-2-150.
What noise limit applies to a Weld County data center?
Beyond the dB(A) limits in Section 14-9-40 of the county code, no data center can exceed a C-scale limit of 65 dB(C), measured at any point on the subject property boundary. The code states the limit twice: in the site plan standards of Section 23-2-160 and in the special review operation standards of Section 23-2-250.
How large a backup power system can a data center have?
The Section 23-1-90 definition counts backup power systems as ancillary structures only with a total generation capacity of less than fifty (50) megawatts. The definition puts no limit on the data center's own peak electrical load. Backup generation of 50 megawatts or more falls outside what the definition treats as an ancillary system.
How long does a data center approval last if construction stalls?
A Site Plan Review approval terminates 30 days after notice if construction has not started, with continual progress, within three years. The Director of Planning Services can grant a one-time extension of up to 120 days for good cause. A special review permit is vacated if not commenced within three years, and either approval ends after three consecutive years of discontinued use.

Sources & Official References

Other rules in Weld County

All Weld County rules

Compare Weld County to another location·View the Colorado data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Weld County, CO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Data Center Zoning & Siting in Cities Across Weld County