Corvallis, OR Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)
Key Facts
- Use classification
- Data centers = Technology and Support Services
- LI Zone by-right cap
- 20 or fewer employees per shift
- Conditional Development trigger
- More than 20 employees per shift
- CD review body
- Director or Planning Commission (Ch. 2.3)
- Bicycle parking ratio
- 1 per 15,000 sq ft or 10% of staff
- Enforcing office
- Corvallis Community Development / Building Official
Summary
In the City of Corvallis, a data center falls under the Land Development Code's Technology and Support Services use type, and the Limited Industrial (LI) Zone treats it as permitted outright only up to a staffing threshold. Table 3.21-2 lets a facility with 20 or fewer employees per shift move straight to a building permit, but anything larger triggers Conditional Development review under Chapter 2.3 before Community Development can approve it.
Table 3.21-2 - LI Zone Permitted Use Types "P" - Primary use permitted outright. ... "CD" - Primary use subject to approval in accordance with Chapter 2.3 - Conditional Development. ... Technology and Support Services P 20 or fewer employees per shift. Technology and Support Services CD More than 20 employees per shift.
Full Breakdown
Corvallis's Land Development Code folds data centers into the broader Technology and Support Services use type defined in Section 3.0.30.03.cc, which covers any facility used to store and operate computer systems and associated components alongside call centers, customer support centers, and telemarketing centers. In the Limited Industrial (LI) Zone, Chapter 3.21's Table 3.21-2 splits that use type by staffing: a facility with 20 or fewer employees on its largest shift is a Primary use permitted outright, while a facility staffing more than 20 employees per shift needs Conditional Development approval under Chapter 2.3, meaning the Director or Planning Commission must review the specific site plan before Community Development can issue a building permit.
That staffing-based split runs throughout the LI Zone's commercial and industrial use table, applying the same 20-employee threshold to Vocational or Professional Training and Limited Manufacturing. Once a data center clears zoning review, the Code's parking chapter treats it differently again: Table 4.1-2 in Chapter 4.1 sets bicycle parking for the Technology and Support Services - Data Center use type at one space per 15,000 sq. ft. of gross floor area, or 10 percent of total employees on the largest shift, whichever is greater, a far lower ratio than the one-per-1,500-sq.-ft. rate that applies to every other Technology and Support Services use, reflecting how few workers a server floor holds per square foot.
Violations & Fines
Building a staffed data center in the LI Zone without the required Conditional Development approval blocks the permit at the front counter: Section 1.3.20 bars the Building Official from issuing a Building Permit until the Director confirms the proposal complies with the Code, and Section 1.3.40 lets the Director order a halt and withhold or revoke permits if construction departs from what was approved.
Frequently Asked Questions
Is a data center a permitted use in Corvallis's Limited Industrial Zone?
What happens if a Corvallis data center staffs more than 20 people per shift?
Does Corvallis require bicycle parking for data centers?
Can the City of Corvallis revoke a data center's building permit?
Sources & Official References
Other rules in Corvallis
Compare Corvallis to another location·View the Oregon data centers & crypto mining overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.