Costa Mesa, CA Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Dedicated ordinance
None
Industrial zones
MG and MP
Unlisted use
Director similarity finding
Fallback permit
Conditional use permit
Discretionary review
CEQA plus public hearing

Summary

Costa Mesa has no data-center use in its Land Use Matrix. Server facilities locate in the MG and MP industrial zones, permitted by right when the development services director finds similarity to a listed industrial use, and otherwise by conditional use permit.

Any proposed use not listed in the Land Use Matrix shall be reviewed by the development services director to determine its similarity to another listed use. If no substantial similarity exists, the proposed use shall require approval of a conditional use permit prior to establishment of the use.

Source: Costa Mesa Municipal Code Title 13 (Planning, Zoning and Development), Land Use Matrix & Noise ControlView official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4894290; v9 updated 2025-11-18).

Full Breakdown

Costa Mesa's Land Use Matrix, Table 13-30, lists no data center, server farm, or computer facility use. The city's industrial districts are MG, general industrial, and MP, industrial park. Research and development laboratories, light manufacturing, and warehousing of durable and nondurable goods are permitted by right in both. Under Section 13-30(d), a use not listed is reviewed by the development services director for similarity to a listed use; without substantial similarity it requires a conditional use permit, a discretionary approval carrying CEQA review and a Planning Commission hearing. The city has adopted no data-center ordinance and no moratorium.

Violations & Fines

Establishing a data center outside the MG or MP zones, or without a required conditional use permit, is a Municipal Code violation enforced by Costa Mesa code enforcement through citations, administrative fines, and abatement.

Frequently Asked Questions

Where can a data center be built in Costa Mesa?
In the MG general industrial and MP industrial park zones. Table 13-30 has no data-center listing, so the development services director matches the project to the closest listed industrial use.
Does Costa Mesa require a conditional use permit for a data center?
Only when no listed use is substantially similar. Section 13-30(d) then requires a conditional use permit, which brings CEQA review and a Planning Commission hearing.
Costa Mesa has no data-center ordinance. Who do I ask for one?
The City Council and Planning Commission set zoning policy. Contact the Planning Division at planninginfo@costamesaca.gov or (714) 754-5245, or speak at a Planning Commission meeting: https://www.costamesaca.gov/government/departments-and-divisions/economic-and-development-services/planning

Sources & Official References

Other rules in Costa Mesa

All Costa Mesa rules

California rules heatmap·Compare Costa Mesa to another location·View the California data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Costa Mesa, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Data Center Zoning & Siting in Nearby Cities

How other cities in Orange County handle data center zoning & siting.

Newport Beach, CA
Light Restrictions
Orange, CA
Some Restrictions
Huntington Beach, CA
Some Restrictions
Garden Grove, CA
Few Restrictions
Santa Ana, CA
Significant Restrictions
Irvine, CA
Significant Restrictions
Anaheim, CA
Heavy Restrictions