Skip to main content
CityRuleLookup

Anaheim, CA Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)

Heavy Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified July 2026

Key Facts

Zone
Industrial (I), Table 10-A
Code
Sec. 18.10.030.060
Use Class
No data-center class exists
Unlisted Uses
Prohibited in base I zone
Determination
Director classifies (Sec. 18.36.020)

Summary

Anaheim's Zoning Code has no data-center use class. Because the Industrial (I) zone's Table 10-A doesn't list them and unlisted uses are prohibited, the Planning & Building Director must classify a data center under an existing use before it can be built.

Any use class that is not listed in Tables 10-A, 10-B or 10-C is not permitted.

Source: Anaheim Municipal Code (Title 18 Zoning; Chapter 6.70 Sound Pressure Levels)View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-28: Code: Supplement contains: Local legislation current through Ord. 6627, passed 8-11-2026 | Zoning: Local legislation current through Ord. 6627, passed 8-11-2026).

Full Breakdown

Under Municipal Code Section 18.10.030, the Industrial (I) zone permits uses only if they appear in Table 10-A, and subsection .060 states any use class not listed is not permitted. No "data center" or "server farm" class exists anywhere in Title 18. Section 18.36.020 gives the Planning & Building Director authority to interpret which existing class a data center fits: for example "Industry," "Research & Development," or "Warehousing & Storage-Enclosed," all permitted by right in the I zone, while a large on-site substation ("Utilities-Major") needs a conditional use permit. Uses fitting no class follow the Section 18.66.040 unlisted-use path, ending in a Planning Commission CUP. Discretionary approvals trigger CEQA review.

Violations & Fines

Building or operating a data center in the Industrial zone without the required use-classification determination or, where applicable, a conditional use permit is a zoning violation enforced by Anaheim Planning & Building code enforcement.

Frequently Asked Questions

Can you build a data center in Anaheim?
Not by right under a named use. Anaheim's code has no data-center class, so the Planning & Building Director must classify it under an existing Industrial-zone use, often "Industry," and CEQA review applies to discretionary approvals.
Does Anaheim have a data-center ordinance?
No. Anaheim has no dedicated data-center ordinance, cap, or moratorium. To weigh in on how these projects are sited, contact Anaheim Planning & Building or address the City Council and Planning Commission.

Sources & Official References

Other rules in Anaheim

All Anaheim rules

California rules heatmap·Compare Anaheim to another location·View the California data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Anaheim, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Data Center Zoning & Siting in Nearby Cities

How other cities in Orange County handle data center zoning & siting.

Newport Beach, CA
Light Restrictions
Orange, CA
Some Restrictions
Huntington Beach, CA
Some Restrictions
Garden Grove, CA
Few Restrictions
Santa Ana, CA
Significant Restrictions
Irvine, CA
Significant Restrictions
Costa Mesa, CA
Significant Restrictions