Denton, TX Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Residential setback
100 feet minimum
Noise limit
60 dBA at property line
MR/SC floor area cap
55,000 sq ft per lot
Screening required
Opaque wall, fence, or landscaping
Max fine
$2,000/day (Sec. 1-12)

Summary

Denton's zoning code allows warehouse and modular data centers only in specific commercial and industrial districts, requiring a 100-foot residential setback, opaque screening, and a formal noise study before construction begins.

On-site electrical equipment, and any associated outdoor storage area shall be setback no less than one-hundred (100) feet from an adjacent residential zoning district or an existing residential use, measured from the property line. ... Data center operations, including on-site electrical equipment, shall not cause any noise measuring more than sixty (60) dba on the A-weighting utilizing properly calibrated sound measuring instrumentation measured at the property line, or shall not cause an increase in the ambient noise level in the area more than 3 dba.

Full Breakdown

The Denton Development Code treats data centers as an industrial use, permitted by-right in some districts and requiring a Specific Use Permit in others (DDC § 5.3.6, Industrial Uses. Data Center, Warehouse and Data Center, Modular standards). In the MR and SC districts, floor area is capped at 55,000 square feet per lot. On-site electrical equipment and outdoor storage must sit at least 100 feet from any adjacent residential zoning district or use and be opaquely screened with masonry, wall, or evergreen landscaping. Applicants must also submit an environmental noise and vibration assessment showing operations won't exceed 60 dBA at the property line or raise ambient noise more than 3 dBA.

Violations & Fines

Violating Denton's zoning or Development Code provisions carries up to a $2,000 fine under the city's general penalty clause (Sec. 1-12), with each day of continued violation treated as a separate offense.

Frequently Asked Questions

Can a data center be built anywhere in Denton?
No. Data centers are allowed only in certain zoning districts under the Denton Development Code, and some districts require a Specific Use Permit rather than by-right approval.
Does Denton limit data center noise?
Yes. Operations can't exceed 60 dBA at the property line or raise ambient noise more than 3 dBA, verified by a required noise and vibration study submitted with the application.

Sources & Official References

Other rules in Denton

All Denton rules

Texas rules heatmap·Compare Denton to another location·View the Texas data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Denton, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.