Key Facts

Setback
100 ft minimum from residential/OR/A1/Ag-Res lines
Buffer
75 ft landscaped buffer along same lines
Building height
20 ft minimum
Fencing
Chain-link must be hidden from right-of-way
Effective
Section created March 6, 2025

Summary

Any data center in unincorporated Forsyth County must sit back at least 100 feet from residential, OR, A1, or Ag-Res property lines and keep a separate 75-foot planted buffer along those same lines under Unified Development Code Section 16-4.10. Buildings must stand at least 20 feet tall, and any chain-link fencing has to stay hidden from the public right-of-way.

These county ordinances apply to unincorporated areas of Forsyth County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

The following requirements must be met for all data centers: (a)A 100-foot minimum setback is required along all lot lines abutting a residential, OR, A1, or Ag-Res zoning district.(b)A 75-foot minimum buffer is required along all lot lines abutting a residential, OR, A1, or Ag-Res zoning district.(c)Buildings shall be a minimum of 20 feet in height.(d)If used, no chain link fence shall be visible from the right-of-way.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 43).

Full Breakdown

10 of the Unified Development Code, created March 6, 2025 as data center development surged around Forsyth County's Georgia 400 corridor, sets the dimensional and site-design floor every data center must clear before the county issues a land disturbance or building permit. Where a data center site borders a residential, OR (office-residential), A1 (agricultural), or Ag-Res zoning district, the building must be set back a minimum of 100 feet from that lot line, and a separate 75-foot landscaped buffer is required along the same boundary, stacking the setback and buffer rather than layering them on top of each other.

Buildings must be at least 20 feet in height, a floor rather than a ceiling, aimed at avoiding the low, sprawling warehouse footprint that maximizes ground disturbance. If the developer uses chain-link fencing anywhere on the site, none of it may be visible from the public right-of-way, forcing either an alternate fencing material along road frontage or a screening buffer in front of it. These standards sit alongside separate generator-use and noise limits in the same section, and alongside the county's water-use restrictions on hydro cooling systems, which cannot draw on or discharge into the county water system without the Director of Water and Sewer's approval.

The provision applies countywide to unincorporated Forsyth County, not just a designated overlay, on top of whatever conditional-use approval the underlying zoning district already requires for a data center.

Violations & Fines

A data center site plan that does not meet the 100-foot setback, 75-foot buffer, or 20-foot minimum height cannot be approved administratively; the applicant must seek a variance or, for non-numerical design issues, a public hearing before the Board of Commissioners. Visible chain-link fencing found during inspection can hold up a certificate of occupancy until it is replaced or screened.

Frequently Asked Questions

How close to a house can a data center be built in Forsyth County?
At least 100 feet, measured from the lot line, whenever the data center site abuts land zoned residential, OR, A1, or Ag-Res, per UDC Section 16-4.10(a). A separate 75-foot landscaped buffer runs along that same boundary line, so the true separation between a data center building and adjoining residential land is effectively both distances combined.
Is there a minimum size requirement for data center buildings?
Yes, but it is a height floor, not a size cap: Section 16-4.10(c) requires data center buildings to be at least 20 feet tall. The code does not set a maximum height for data centers in this section, so any height ceiling instead comes from the underlying zoning district's general standards.
Can a data center use chain-link fencing in Forsyth County?
Only if none of it is visible from the public right-of-way. Section 16-4.10(d) allows chain-link fencing on a data center site but requires it to be hidden from the road, typically by placing it behind landscaping, another fence material, or setting it back from street-facing property lines.

Sources & Official References

Other rules in Forsyth County

All Forsyth County rules

Compare Forsyth County to another location·View the Georgia data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Forsyth County, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.