Piscataway, NJ Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)
Key Facts
- Where data centers are permitted
- Warehouse/Light Industrial Redevelopment Overlay Zone only
- Max principal building height
- 60 feet
- Setback from street/lot lines
- 25 feet
- Buffer from residential use
- 200 feet minimum
- Overlay floor area cap
- 2,400,000 sq ft aggregate
- Prohibited in overlay
- Cellular towers and antennas
Summary
Piscataway Township permits data centers as a principal use only within the Warehouse/Light Industrial Redevelopment Overlay Zone along River Road, defined at Section 21-30.3. The overlay caps commercial building height at 60 feet, requires a 25-foot setback from streets and lot lines, and bars any commercial building within 200 feet of a permitted residential use.
§ 21-30.3. Permitted Principal Uses. ... a. All uses permitted in the LI-1 and LI-5 Zones. b. Data centers. ... § 21-30.6. Maximum Building Height. ... a. No principal commercial building shall exceed 60 feet in height. Mezzanine areas are permitted within the buildings, and shall not be treated as a "story." ... § 21-30.8. Setback Requirements. ... b. No commercial building shall be located within 200 feet of a permitted residential use.
Full Breakdown
Chapter 21, Zoning, defines a DATA CENTER as 'a large group of networked computer servers typically used by organizations for the remote storage, processing, or distribution of large amounts of data' in the Township's general definitions section. That use is a listed permitted principal use only within the Warehouse/Light Industrial Redevelopment Overlay Zone District established by Section 21-30.1 for Block 421.1, Lots 1.03, 1.04 and 6.03 along River Road, an area designated 'in need of redevelopment.' Section 21-30.3 lists data centers alongside self-storage facilities, training centers and limited retail (capped at 2% of gross floor area) as permitted principal uses, on top of everything already allowed in the LI-1 and LI-5 Light Industrial Zones.
A data center sited there is capped by Section 21-30.6 at 60 feet for the principal commercial building, with mezzanine levels not counted as a separate story; accessory buildings are capped at 25 feet and two stories. Section 21-30.7 limits the whole overlay to 2,400,000 square feet of aggregate gross leasable floor area and 25% building coverage. Section 21-30.8 requires a 25-foot setback from all street lines and external lot lines (with an exception allowing a zero-foot line at the Middlesex Borough boundary for cross-boundary development) and bars any commercial building within 200 feet of a permitted residential use.
Cellular towers and antennas are expressly prohibited in the overlay regardless of underlying zoning. Outside this overlay, the Zoning Ordinance's district use tables reviewed for this record do not list data centers as a permitted principal use, so a data center proposed elsewhere in the Township would need a use variance from the Zoning Board of Adjustment.
Violations & Fines
Building a data center outside the Warehouse/Light Industrial Redevelopment Overlay Zone without an approved use variance from the Zoning Board of Adjustment violates the Zoning Ordinance's permitted-use limits. Exceeding the 60-foot principal building height, encroaching within 200 feet of a residential use, or installing a cellular tower or antenna in the overlay violates Sections 21-30.6, 21-30.8 and 21-30.5, enforced by the Zoning Officer through a stop-work order or Municipal Court complaint.
Frequently Asked Questions
Where in Piscataway Township can a data center be built?
How tall can a data center building be?
How close can a data center be to homes?
What does Piscataway's code mean by 'data center'?
Sources & Official References
Other rules in Piscataway
Compare Piscataway to another location·View the New Jersey data centers & crypto mining overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.