Pomona, CA Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)

Few Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified July 2026

Key Facts

Dedicated ordinance
None
By-right use
"Data processing" in M zone
Industrial zones
C-IND, M, M-1
Permit level
By-right; ministerial building permit
Discretionary review
CEQA if applicable

Summary

Pomona has no data-center ordinance, but its Zoning Ordinance lists "data processing" as a by-right permitted use in the "M" Special Industrial Zone. Data centers also fit the M-1 light-industrial and C-IND commercial-industrial districts, permitted by right when housed in a fully enclosed building.

The following buildings, structures and uses, either singly or in combination, are permitted in the "M" zone ... (a) Light manufacturing, research, assembly, testing and repair of components, devices, equipment and systems, and parts and components, such as, but not limited to: ... Data processing.

Source: Pomona Zoning Ordinance (Appendix I) & City Code Ch. 18 (Noise and Vibration Control)View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: City Code: Supplement 31).

Full Breakdown

Pomona's Zoning Ordinance (Appendix I) does not define "data center" as a use. The "M" Special Industrial Zone, Sec. .396, permits "data processing" outright among light-manufacturing and research uses, so a server facility is allowed by right where operations sit within a totally enclosed building. The M-1 Light Industrial and C-IND Commercial-Industrial districts admit the same industrial and warehousing uses. No conditional use permit targets data centers; ministerial building and electrical permits apply. A discretionary project still triggers CEQA review. Unlike Los Angeles County, Pomona adopted no moratorium and ordered no study.

Violations & Fines

Operating a data center outside Pomona's industrial zones, or outside a totally enclosed building where required, violates the Zoning Ordinance, enforced by Planning and Code Enforcement through stop-work orders, penalties, and abatement.

Frequently Asked Questions

Where can data centers be built in Pomona?
In Pomona's industrial districts - C-IND, M Special Industrial, and M-1 Light Industrial. The "M" zone even lists "data processing" as a permitted use, so a server facility is allowed by right inside a fully enclosed building.
Does Pomona require a special permit for a data center?
No. Pomona has no data-center-specific permit. A server facility is permitted by right as an industrial use, needing only ministerial building and electrical permits. A discretionary project still undergoes CEQA review.
Does Pomona have a data-center ordinance or moratorium?
No. Pomona has adopted no data-center ordinance, moratorium, or study. Residents wanting tailored siting or noise standards can petition the City Council or Planning Commission through the Planning Division.

Sources & Official References

Other rules in Pomona

All Pomona rules

California rules heatmap·Compare Pomona to another location·View the California data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in Pomona, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Data Center Zoning & Siting in Nearby Cities

How other cities in Los Angeles County handle data center zoning & siting.

Long Beach, CA
Light Restrictions
Los Angeles, CA
Some Restrictions
El Monte, CA
Some Restrictions
Pasadena, CA
Some Restrictions
Torrance, CA
Some Restrictions
Palmdale, CA
Some Restrictions
Lakewood, CA
Some Restrictions
Norwalk, CA
Some Restrictions