Victoria, TX Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)
Key Facts
- Noise limit
- 55 decibels max at property line
- Crypto mining setback
- 500 feet from residential use
- Minimum lot size
- 10,000 square feet
- Governing ordinance
- No. 2025-66, effective 4-15-2025
- Code section
- UDO Sec. 21-146(e)
Summary
Victoria's Unified Development Ordinance requires data centers and crypto mining farms to secure all county, state, and federal permits before approval, cap noise at 55 decibels at the property line, and keep crypto mining rigs at least 500 feet from any residential use.
(e)Data Center or Crypto Mining Farm. (1)Any Data Center or Crypto Mining Farm shall comply with all applicable Victoria County, State of Texas, and Federal regulations and permit requirements prior to approval. (2)Any Data Center or Crypto Mining Farm shall: a.not produce more than fifty-five (55) decibels of sound at any time, as heard from any property line. (3)Crypto Mining Farms shall be located at least five hundred (500) feet from any residential use, as measured from the property line.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 42).
Full Breakdown
Adopted April 15, 2025 by Ordinance 2025-66, Sec. 21-146(e) of the Unified Development Ordinance places data centers and crypto mining farms under the Infrastructure use category. Both uses must comply with all applicable Victoria County, State of Texas, and federal regulations and permit requirements before city approval, and neither is allowed to produce more than 55 decibels of sound at any time, measured from any property line. Crypto mining farms carry one added standard: they must sit at least 500 feet from any residential use, measured from the property line. The city's use table also sets a minimum lot size of 10,000 square feet and a parking ratio of roughly one space per 2,000 square feet of gross floor area.
Violations & Fines
Building without the required permits, exceeding the 55-decibel limit, or siting a crypto mining farm within 500 feet of a residential use is a UDO violation; the city can withhold permits and certificates of occupancy until it is corrected.
Frequently Asked Questions
Does Victoria allow crypto mining farms?
Is there a noise limit for data centers in Victoria?
When did Victoria adopt these siting rules?
Sources & Official References
Other rules in Victoria
Texas rules heatmap·Compare Victoria to another location·View the Texas data centers & crypto mining overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.