York County, VA Data Centers & Crypto Mining: Data Center Zoning & Siting (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Enforcing agency
Zoning Administrator, Dept. of Planning and Development Services
Setback, non-residential lines
100 feet
Setback, residential lines
500 feet
Required buffer
50-foot evergreen Type 50 Transitional Buffer
Max height
75 feet unless Board approves more
Noise limit
55 dBA or 65 dBC at property line
Generator testing window
Mon-Fri, 5:00 pm to 8:00 pm, one unit

Summary

In York County, Virginia, data centers need a special use permit from the Board of Supervisors and must meet siting standards under Sec. 24.1-489.1: buildings sit back 100 feet from non-residential lines and 500 feet from residential property lines, sit behind a 50-foot evergreen buffer, and cap out at 75 feet unless the Board approves more height.

These county ordinances apply to unincorporated areas of York County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

Any special use permit application submitted under the provisions of this section shall be accompanied by the following items which, in addition to the standards set forth below, shall be considered by the Planning Commission and Board of Supervisors: ... (g)Data center structures and their ancillary equipment must be set back 100 feet from any non-residential zoned property lines and 500 feet from residential property lines.(h)All data center developments shall be surrounded by a buffer of at least fifty feet (50') in width, which shall be landscaped with evenly distributed evergreen vegetation, in accordance with the provisions of Article II, Division 4 of this chapter, to meet the Type 50 Transitional Buffer standards.

Full Breakdown

York County's Board of Supervisors treats data centers as a special use permit category under Sec. 24.1-489.1 of the zoning ordinance, administered by the Department of Planning and Development Services. An applicant must submit a letter from the electric utility confirming substation and transmission capacity at each project phase and at full build-out, and, if the facility uses water cooling, a letter from the public water purveyor confirming supply for full operating capacity; above-ground liquefied petroleum gas storage is barred outright. Every data center must tie into public water, since wells are prohibited as a supply source, and must employ conservation methods such as rainwater harvesting, subject to county approval.

On siting itself, structures and their ancillary equipment must sit back 100 feet from any non-residential property line and 500 feet from any residential property line, and the whole development needs a 50-foot evergreen buffer meeting the county's Type 50 Transitional Buffer standard. Building height tops out at 75 feet unless the Board grants more. Noise is capped at 55 A-weighted decibels or 65 C-weighted decibels at the property line, whichever is greater, backed by a pre- and post-development sound study, and on-site generator testing is confined to one unit at a time, Monday through Friday, 5:00 p.m. to 8:00 p.m.

Fire lane access, a 33-foot drive-aisle turning radius, and an evacuation plan approved by the Department of Fire and Life Safety round out the operational conditions. Owners must recertify electricity and water use every five years, and if a facility sits idle for 30 days straight, the Zoning Administrator can ultimately order the equipment dismantled and removed within 180 days.

Violations & Fines

Operating a data center in York County without an approved special use permit, or beyond the water, noise, or setback conditions the Board of Supervisors attaches, is a zoning violation the Zoning Administrator enforces. Failing to recertify electricity and water use every five years, or ignoring a Zoning Administrator's order to dismantle idle equipment within 180 days, exposes the owner or lessee to a mandatory removal order the county can carry out at the owner's expense.

Frequently Asked Questions

Does York County require a special permit for a data center?
Yes. Sec. 24.1-489.1 requires a special use permit reviewed by the Planning Commission and Board of Supervisors, with a letter from the electric utility confirming substation capacity and, for water-cooled facilities, a letter from the public water purveyor before the county issues any approval.
How far must a data center sit from homes in York County?
The structure and its ancillary equipment must be set back 500 feet from any residential property line and 100 feet from non-residential property lines, plus a 50-foot landscaped buffer meeting the county's Type 50 Transitional Buffer standard around the whole site.
What happens if a York County data center sits idle?
After 30 continuous days offline, the owner must report to the Zoning Administrator within seven days. If operations won't resume, the Zoning Administrator can order the equipment dismantled and removed from the site within 180 days at the owner's expense.

Sources & Official References

Other rules in York County

All York County rules

Compare York County to another location·View the Virginia data centers & crypto mining overview

Get notified when Data Center Zoning & Siting in York County, VA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.