Key Facts

Trigger
1 acre or more of land disturbance
Plan certifier
PE, landscape architect, or Tier B surveyor
Existing sites
Denuded areas revegetated on county-approved schedule
Drainage ways
Must be vegetated or lined to stop erosion
Penalty
Up to $1,000 per day for noncompliance
Design guide
Pickens County Stormwater Design Manual sets specs

Summary

Any land-disturbing activity of one acre or more in unincorporated Pickens County must include a sediment and erosion control plan under Code Section 38-331, showing the site's topography, drainage, soil types, and the specific measures used to stop erosion and sedimentation during construction. Older, already-developed sites are not exempt: Section 38-333 requires denuded areas to be revegetated and cuts, slopes, and drainage ways stabilized on a schedule the county approves.

These county ordinances apply to unincorporated areas of Pickens County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

The sediment and erosion control plan shall accurately describe the potential for soil erosion and sedimentation problems likely to result from the land-disturbing activity, and shall explain and illustrate the measures that is to be taken to control these problems. The plan shall conform to the requirements found in the stormwater design manual and shall include the following: →Project description→A topographic map→All existing drainage ways→A general description of existing land cover→Stands of existing trees, as they are to be preserved upon project completion→Approximate limits of proposed clearing, grading and filling ... (1)Denuded areas must be vegetated or covered under the standards and guidelines specified in the stormwater design manual and on a schedule acceptable to Pickens County.(2)Cuts and slopes must be properly covered with appropriate vegetation and/or retaining walls constructed.(3)Drainage ways shall be properly covered in vegetation or secured with riprap, channel lining, etc., to prevent erosion.

Full Breakdown

The plan required by Section 38-331 must accompany any land-disturbance permit application for one acre or more of disturbance, and it must be stamped by a licensed professional engineer, landscape architect, or Tier B land surveyor per Section 38-323. It has to describe the potential for erosion and sedimentation and show how the project controls it, including a project description, a topographic map, all existing drainage ways, existing land cover and soil types, stands of trees to be preserved, the approximate limits of clearing, grading, and filling, existing and post-construction stormwater flows leaving the site, the proposed drainage network and drain tile or waterway sizes, the sequence of work, specific remediation measures, and details for rock pads and wash-down pads, all conforming to the Pickens County Stormwater Design Manual.

Section 38-333 extends duties to property that was already developed before the article was adopted: denuded areas must be vegetated or covered on a schedule the county accepts, cut slopes must be covered with vegetation or retaining walls, and drainage ways must be vegetated or lined with riprap or channel lining to stop erosion, with trash and debris cleared from them. Pickens County notifies owners in writing of specific drainage, erosion, or sediment problems and sets a compliance deadline, and can inspect any site, built before or after the article, on a routine, random, or complaint basis to confirm the facilities still function within their design limits.

Violations & Fines

Erosion-control violations fall under the same enforcement article as the stormwater permit: Pickens County can issue a stop-work order, withhold a certificate of occupancy, and suspend or revoke the permit until the site is stabilized. After notice and a cure period, unremedied violations draw a civil penalty of up to $1,000.00 per day, and intentional or flagrant violations can bring a criminal citation with a fine up to $1,000.00, up to 60 days in jail, or both.

Frequently Asked Questions

What must a sediment and erosion control plan show in Pickens County?
Section 38-331 requires a project description, topographic map, existing drainage ways, land cover and soil types, tree stands to be preserved, clearing and grading limits, the proposed drainage network, projected work sequence, and specific measures to control erosion and sedimentation, all conforming to the county's Stormwater Design Manual.
Who has to sign off on an erosion control plan?
Section 38-323 requires professionally certified site plans, and erosion and sediment control plans, stamped and sealed by a licensed professional engineer, landscape architect, or Tier B land surveyor before Pickens County will accept the application.
Do existing, already-built properties have erosion control duties in Pickens County?
Yes. Section 38-333 requires denuded areas on existing developed sites to be vegetated or covered on a schedule the county approves, cuts and slopes to be stabilized with vegetation or retaining walls, and drainage ways to be vegetated or lined with riprap to stop erosion.
What can Pickens County do if my site is eroding without an approved plan?
Under Section 38-337, the county can issue a stop-work order, withhold a certificate of occupancy, suspend or revoke the permit, and impose a civil penalty of up to $1,000 per day the violation continues, with criminal fines up to $1,000 or 60 days in jail for flagrant violations.

Sources & Official References

Other rules in Pickens County

All Pickens County rules

Compare Pickens County to another location·View the South Carolina environmental rules overview

Get notified when Erosion Control in Pickens County, SC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.