Bartow County, GA Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit trigger
1 acre or more of land disturbance
Stabilization deadline
7 days after disturbance
Stream buffer
25 ft (50 ft on trout streams)
Surety required
$3,000 per acre disturbed
Construction exit fine
$1,000 per day per exit
Governing law
Bartow County Code Ch. 34, Art. IV

Summary

Unincorporated Bartow County requires a land disturbance permit and an approved erosion, sedimentation and pollution control plan before any land-disturbing activity of an acre or more begins. Disturbed areas must be stabilized within seven days, and a 25-foot buffer, 50 feet along trout streams, protects the banks of state waters.

These county ordinances apply to unincorporated areas of Bartow County. Incorporated cities within the county may have their own rules that take precedence over county-level regulations.

(7)Temporary vegetation or mulching shall be employed to protect exposed critical areas during development. Exposed areas shall be vegetated or otherwise stabilized within seven days after disturbance. Temporary vegetation cannot be used as permanent vegetation. ... (15)Except as provided in paragraph (16) of this subsection, there is established a 25-foot buffer along the banks of all state waters, as measured horizontally from the point where vegetation has been wrested by normal stream flow or wave action

Full Breakdown

Bartow County's Soil Erosion and Sedimentation and Pollution Control Ordinance, Chapter 34, Article IV, requires anyone disturbing an acre or more of land, or land within a larger common plan of development, to obtain a land disturbance permit from the county engineer before work begins. 00 per acre disturbed. Best management practices must follow the state's Manual for Erosion and Sediment Control in Georgia: exposed critical areas must be vegetated or otherwise stabilized within seven days of disturbance, temporary vegetation cannot substitute for permanent cover, and cut-fill operations, grading and drainage must be designed to minimize erosion and keep sediment off adjoining property.

A 25-foot undisturbed buffer runs along the banks of all state waters, measured from the point vegetation has been wrested by normal stream flow, widening to 50 feet along designated trout streams; the director can grant a narrower variance only where a roadway drainage structure must cross or for limited utility line crossings. Every land-disturbing site must maintain a stabilized construction exit to keep mud off public roads, and tracking soil onto pavement is itself a separate violation. Even completed, non-permitted properties have a continuing duty under section 34-268 to keep vegetation in place and prevent visible sediment from washing onto a neighbor's land or into county ditches.

Violations & Fines

Failing to install a required construction exit carries a $1,000.00-per-day fine. Tracking sediment onto county or state roadways, or letting visible sediment escape onto another owner's property, is a separate violation of the ordinance under section 34-267(f), and a completed property that stops maintaining ground cover faces a $150.00 fine per rain event under section 34-268(c). The county engineer can also issue stop work orders, suspend or revoke the permit, and seek injunctive relief and attorney's fees in superior court.

Frequently Asked Questions

When does Bartow County require an erosion control permit?
A land disturbance permit is required whenever a project disturbs one acre or more, or is part of a larger common plan of development or sale that reaches that threshold, under section 34-281 of the Bartow County Code; single-family lots disturbing less than one acre and not part of a larger plan are exempt under section 34-255(4).
How wide is the required stream buffer?
A 25-foot natural, undisturbed buffer protects the banks of state waters, widening to 50 feet along streams designated as trout waters, measured horizontally from the point vegetation has been wrested by normal stream flow, under section 34-267(c)(15) and (16) of the Bartow County Code.
How fast must a builder stabilize disturbed ground?
Exposed critical areas must be vegetated or otherwise stabilized within seven days after the ground is disturbed, and temporary vegetation or mulch alone cannot serve as permanent cover under section 34-267(c)(7) of the Bartow County Code.
What is the penalty for tracking mud onto the road?
Tracking or carrying soil onto a county or state roadway is a separate violation carrying its own citation, and the county can bill the developer for cleanup costs and withhold further building permits until the bill and any $1,000-per-day construction exit fine are paid.

Sources & Official References

Other rules in Bartow County

All Bartow County rules

Compare Bartow County to another location·View the Georgia environmental rules overview

Get notified when Erosion Control in Bartow County, GA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.