Caddo Parish, LA Environmental Rules: Erosion Control (2026)
Key Facts
- Governing law
- Code of Ordinances §§ 46-57 to 46-61
- Stabilization deadline
- 14 days after work stops on that area
- Temporary BMP removal
- Within 30 days of final stabilization
- Design storm standard
- Two-year, 24-hour storm event
- SWPPP preparer
- CPESC or licensed professional civil engineer
- Civil penalty
- $500.00 per day, per violation
Summary
Caddo Parish requires every construction site in the unincorporated parish to stabilize exposed soil within 14 days of work stopping, and major developments of one acre or more must file a stormwater pollution prevention plan prepared by a licensed engineer or CPESC.
In addition to any state and federal permit requirements, the following items shall be required and shall be addressed in the stormwater pollution prevention plan for all major developments: (1)Stabilization and sediment trapping. All exposed and unworked soils, including soil stockpiles, shall be stabilized by suitable application of BMPs which protect soil from the erosive forces of raindrop impact and flowing water... Stabilization BMPs shall be initiated as soon as practicable in portions of the site where construction activities have temporarily or permanently ceased, but in no case more than 14 days after the construction activity in that portion of the site has temporarily or permanently ceased... (15)Erosion control design storm event. Facilities designed for the control of erosion and sedimentation shall be designed for the erosion and sedimentation control design storm event, defined as the two-year, 24-hour duration storm.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 26 | Unified Development Code: Supplement 2).
Full Breakdown
Article III of Chapter 46 splits erosion and sediment control duties by project size. Every minor development, meaning any land-disturbing activity under one acre, must limit construction traffic to a single stabilized access route, stabilize all exposed soil with BMPs like sod, mulch or compacted base material, protect neighboring parcels with buffer strips or sediment barriers, and keep those measures maintained (§ 46-57). Major developments of one acre or more must go further: they must demonstrate compliance through a stormwater pollution prevention plan (SWPPP) that only a certified professional in erosion and sediment control or a licensed professional civil engineer may prepare, and the director can request it before issuing a permit (§ 46-59).
Section 46-60 lists fifteen specific minimum requirements for those SWPPPs, including stabilizing exposed and unworked soils, including stockpiles, within no more than 14 days after construction activity on that portion of the site stops; removing all temporary erosion controls within 30 days of final site stabilization; limiting open utility trenches to no more than 500 feet at a time; and designing temporary conveyance channels to withstand a two-year, 24-hour storm. Facilities built specifically to control erosion and sedimentation must be engineered for that same two-year, 24-hour design storm (§ 46-60(15)).
The director may also require additional or different erosion controls beyond what was originally approved if the parish determines the existing measures aren't containing erosion from the site (§ 46-61), and can order repairs to a hazardous erosion condition, or make emergency repairs and bill the property owner, if the situation is severe enough (§ 46-73).
Violations & Fines
A site out of compliance with Article III is subject to a stop-work order halting all construction except authorized erosion-control work (§ 46-65), and the director may seek injunctive relief or revoke permits under the chapter's nuisance-abatement authority (§ 46-62). Notices of violation carry the same cumulative civil penalty structure as the rest of Chapter 46: $500.00 per day per violation, with a 21-day correction window and a 20-day appeal to the parish commission (§ 46-66, § 46-68).
Frequently Asked Questions
How fast must exposed soil be stabilized on a Caddo Parish construction site?
Who can prepare a required stormwater pollution prevention plan in Caddo Parish?
What storm event must Caddo Parish erosion-control structures be designed for?
Sources & Official References
Other rules in Caddo Parish
Compare Caddo Parish to another location·View the Louisiana environmental rules overview