Cedar Rapids, IA Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Major permit threshold
1 acre or more disturbed
Minor permit threshold
>1/4 acre to <1 acre, or new single-family home
Fill exemption
Under 25 cubic yards per 12 months
Max finish slope near property line
3:1 within 15 feet of line
Appeal deadline
20 days to Director or designee
Enforcing official
City Stormwater Official, Public Works Dept.

Summary

Cedar Rapids requires an erosion control permit before any land-disturbing activity in the city: a major permit for sites of one acre or more, a minor permit for sites between a quarter-acre and one acre and for all new single-family homes. The City Stormwater Official issues and enforces permits under Chapter 71.

(f)Except as provided in Section 71.04, Minor Erosion Control Permit Required, no person shall engage in land-disturbing activities within the City unless they have received an erosion control permit from the City. ... (a)Sites or common plans of development or sale that will result in a total disturbed area of one or more acres shall obtain a major erosion control permit prior to any land-disturbing activities. ... (a)Sites or common plans of development or sale that will result in a disturbed area of greater than one-quarter acre, but less than one acre and all new single-family dwellings shall obtain a minor erosion control permit prior to any land-disturbing activity.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 24).

Full Breakdown

Chapter 71 of the Cedar Rapids Municipal Code, repealed and reenacted by Ordinance No. 05. 03(a)); it requires a Stormwater Pollution Prevention Plan (SWPPP) meeting General Permit No. 2 requirements, payment of the permit fee, and a Soil Quality Plan. 04(a)); the application must include a dimensioned drawing showing property lines, easements, the limits of disturbance, proposed sediment controls, a concrete washout facility and a rock entrance drive. 05 exempts crop production, cemetery graves, emergencies posing immediate danger, and fill of less than 25 cubic yards in a 12-month period. 07(f)). Permits are tied to the site owner's Iowa DNR General Permit No. 04(b)).

Violations & Fines

The City Stormwater Official may inspect any site and issue a notice to comply with a deadline; missing that deadline is a separate violation (Section 71.12(b)). A notice of violation can order work stopped, require repair and cleanup, and withhold building or occupancy permits, and it is filed with the County Recorder's Office; each day of continued noncompliance is a separate violation (Section 71.12(c)). Violations are enforceable by civil action, including injunctive relief, or as a municipal infraction under Iowa Code Section 364.22 (Section 71.15). If the City cleans up sediment tracked off-site, it invoices the responsible party for its actual cost, which becomes a lien on the property if unpaid within 30 days (Section 71.14).

Frequently Asked Questions

Do I need a permit to build a single new house in Cedar Rapids?
Yes. Section 71.04(a) requires a minor erosion control permit for all new single-family dwellings regardless of how much land is disturbed, in addition to any site that disturbs more than a quarter-acre but less than one acre.
What triggers a major erosion control permit instead of a minor one?
Any site or common plan of development or sale that will disturb one acre or more needs a major permit under Section 71.03(a), which requires a full Stormwater Pollution Prevention Plan certified by a design professional, not just the minor permit's dimensioned drawing.
Is any construction work exempt from Cedar Rapids' erosion control permit?
Section 71.05 exempts crop production activities, cemetery graves, emergencies posing immediate danger to life or property, and fill totaling less than 25 cubic yards in any 12-month period.
What happens if I miss the City's deadline to fix an erosion problem?
Missing the compliance date in a notice to comply is a separate violation under Section 71.12(b)(2), and each additional day of noncompliance after a notice of violation counts as its own separate violation under Section 71.12(c)(2).

Sources & Official References

Other rules in Cedar Rapids

All Cedar Rapids rules

Compare Cedar Rapids to another location·View the Iowa environmental rules overview

Get notified when Erosion Control in Cedar Rapids, IA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.