Cincinnati, OH Environmental Rules: Erosion Control (2026)
Key Facts
- Operational-plan threshold
- >1,000 cu yd or ≥1 acre disturbed
- Reviewing utility
- Cincinnati Stormwater Management Utility
- Max slope
- 3 horizontal to 1 vertical
- Residential-zone deadline
- 1 year from permit issuance
- Compliance certification
- Every 6 months for >1,000 cu yd permits
Summary
Cincinnati requires an excavation and fill permit for grading work, and bars issuing one for any excavation or fill moving more than 1,000 cubic yards or disturbing an acre or more without a detailed operational plan approved by the Stormwater Management Utility.
1113-03.1 Operational Plan: An excavation and fill permit shall not be issued for an excavation or fill comprising the movement of more than 1,000 cubic yards of material or disturbing one acre or more (whichever is more restrictive), unless the permit application is accompanied by an operational plan determined by the Cincinnati Stormwater Management Utility as sufficient to ensure that the operations are not offensive or objectionable due to erosion, siltation, dust or construction site pollutants.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 48 Update 4).
Full Breakdown
1 sets the core threshold: an excavation and fill permit cannot be issued for an excavation or fill comprising the movement of more than 1,000 cubic yards of material or disturbing one acre or more, whichever is more restrictive, unless the application is accompanied by an operational plan the Cincinnati Stormwater Management Utility determines sufficient to ensure operations aren't offensive or objectionable due to erosion, siltation, dust, or construction site pollutants. That operational plan must include a narrative site description (total area, disturbed area, impervious area estimates, soil data), maps at a scale of at least 1 inch to 50 feet showing contours, drainage patterns, and erosion controls, a construction-phase stormwater narrative, a post-construction stormwater narrative, and a recorded inspection and maintenance plan for permanent stormwater control practices.
The threshold also applies to smaller contiguous excavations under common ownership or control that together exceed 1,000 cubic yards or one acre. 3 lets the director revoke a permit for noncompliance or offensive operations. Separately, § 1113-05 requires setbacks of excavation and fill slope tops and toes from property boundaries and structures sufficient for safety and foundation support, and § 1113-13 lets the director require a performance bond covering restoration costs where early termination would create a hazard.
Violations & Fines
Excavating or filling land without the required permit or operational plan violates Chapter 1113 and, under CBC § 1101-51.1, is punishable as a misdemeanor of the first degree, with each day of continued violation after notice a separate offense. The director may also revoke an excavation and fill permit under § 1113-03.3 if the operational plan is not followed or the work becomes offensive or objectionable due to erosion, siltation, or dust, and can require a performance bond under § 1113-13 to cover restoration costs if work is abandoned before completion.
Frequently Asked Questions
When does a Cincinnati grading project need a detailed operational plan?
How steep can a fill or excavation slope be in Cincinnati?
How long do I have to finish grading work in a Cincinnati residential zone?
Sources & Official References
Other rules in Cincinnati
Compare Cincinnati to another location·View the Ohio environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.