Key Facts

Minimum penalty per offense
$500.00
Continuing violation
each day is a separate offense
Site plan review
required before construction begins
Standard applied
best management practices for sediment/pollutants
Regional standard adopted
Broward County Code §§ 27-196-27-198

Summary

Deerfield Beach requires every construction, development, excavation or alteration project to use best management practices that reduce pollutants and sediment in stormwater runoff. Section 70-199(b) lets the city demand site plans describing erosion and sediment controls before work starts and schedule inspections during and after construction to verify compliance.

(b)Construction sites and construction activities.(1)During and after all construction, development, excavation, and/or alteration operations, structural and non-structural, operators of construction sites and operations shall be required to maintain best management practices with the intent to reduce pollutants and sediment in stormwater run-off.a.Construction and operations site plans and permits may be required and reviewed by the city prior to the initiation of construction operations. Site plans shall include descriptions of structures, procedures and/or control measures designed to reduce and control sediment and pollutant loading either directly or indirectly to stormwater run-off.b.Construction or construction operations over any existing or planned stormwater management system or any such operations causing interference with any stormwater management system shall be prohibited.c.A schedule of inspections for monitoring may be developed to be carried out during and after the construction and operation phases as conditions to the permit to determine and verify compliance with this section.

Full Breakdown

Section 70-199 sets up the city's stormwater management program under Chapter 70, Article VI. Subsection (b), covering construction sites and construction activities, requires that during and after all construction, development, excavation or alteration operations, whether structural or non-structural, operators maintain best management practices with the intent to reduce pollutants and sediment in stormwater runoff. The city may require and review construction and operations site plans and permits before work begins, and those plans must describe the structures, procedures or control measures designed to reduce and control sediment and pollutant loading to stormwater runoff, whether the loading is direct or indirect.

The section separately prohibits construction or construction operations over any existing or planned stormwater management system, or any operation that interferes with one. To confirm ongoing compliance, the city may develop a schedule of inspections carried out during and after both the construction and operation phases, imposed as conditions of the permit. The broader stormwater article that houses this section also bars illicit discharges, alterations to drainage infrastructure without written city approval, and dumping of sediment-bearing litter into any surface area or stormwater system, and it adopts Broward County Code sections 27-196 through 27-198 as the city's minimum surface water and effluent standards.

Together these provisions mean a builder cannot treat silt fencing or erosion barriers as optional paperwork; the city can condition its construction permit on submitted erosion and sediment control measures and can inspect the site to enforce them.

Violations & Fines

Section 70-199(o) sets its own penalty separate from the general Code fine: the city may assess a minimum penalty of $500.00 per offense against a violator, plus additional charges tied to the extent of environmental damage, required mitigation, and clean-up and enforcement costs, and each day a violation continues counts as a separate offense.

Frequently Asked Questions

Does Deerfield Beach require an erosion control plan before construction starts?
Yes. Section 70-199(b) lets the city require and review construction and operations site plans before work begins, and those plans must describe the structures, procedures or control measures a builder will use to reduce and control sediment and pollutant loading to stormwater runoff.
What happens if a construction site lets sediment run into the stormwater system?
It is a violation of Section 70-199 punishable by a minimum $500.00 penalty per offense under subsection (o), with additional charges depending on the environmental damage and the cost of clean-up, remediation and enforcement, and each day the violation continues is treated as a separate offense.
Can the city inspect a construction site for erosion control compliance?
Yes. Section 70-199(b)(1)(c) authorizes a schedule of inspections during and after the construction and operation phases, imposed as conditions of the permit, to determine and verify compliance with the erosion and sediment control requirements.

Sources & Official References

Other rules in Deerfield Beach

All Deerfield Beach rules

Florida rules heatmap·Compare Deerfield Beach to another location·View the Florida environmental rules overview

Get notified when Erosion Control in Deerfield Beach, FL changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Broward County handle erosion control.

Hollywood, FL
Some Restrictions
Pembroke Pines, FL
Some Restrictions
Pompano Beach, FL
Some Restrictions