Des Moines, IA Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit issuer
City engineer
Review time
15 working days
Fee
$120 + $10/acre
Trigger example
500+ sq ft near a waterway
SWPPP required
Sites of 1+ acre

Summary

Des Moines requires a city engineer grading permit before you strip, excavate, fill, or install drainage pipe on most sites, with numeric thresholds triggering the requirement.

No person other than authorized city personnel or city contractors shall grade, strip, excavate, fill, stockpile or cause any non-agricultural earth change on any site, or install drainage pipe in public or private drainageways, without a grading permit issued by the city engineer for any of the following:(1)Platting of land pursuant to chapter 106, pertaining to subdivisions, of this Code.(2)Development of land for which a site plan is required, pursuant to article 9 of chapter 135 of this Code.(3)Installation of utility improvements in trenches that are greater than one foot in width or underground appurtenances with an excavated surface area greater than 400 square feet by a public or private utility company.(4)Excavation or the creation of any disturbed surface of 500 square feet or more of cumulative area within 100 feet of a lake, pond, river, stream, recognized drainageway

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 38 Update 1).

Full Breakdown

Under Municipal Code § 42-86, no one but city crews may grade, strip, excavate, fill, stockpile, or install drainage pipe in public or private drainageways without a city engineer permit: triggered by subdivision platting, required site plans, utility trenches over one foot wide, disturbing 500+ sq ft within 100 feet of a waterway or drainageway, altering stormwater flow onto neighboring property, cuts/fills over 2,500 sq ft, or stockpiling over 5,000 cubic yards of granular material. The engineer can issue a pre-application waiver letter instead. Applications, required under § 42-87, need a licensed engineer, architect, or landscape architect (small residential in-fill jobs under an acre can skip that requirement with the city engineer's sign-off), plus a site plan, topography, drainage area map, and an SWPPP for sites of an acre or more. The city engineer must act within 15 working days under § 42-88 or the application is deemed approved.

Violations & Fines

Grading without a required permit, or failing to complete work per the approved plan, can be treated as a public nuisance under §§ 42-347–42-348; the city may abate it and assess the cost against the property under § 42-91 and Iowa Code § 364.12(3)(h). The application fee is $120 plus $10 per acre or portion thereof (§ 42-89).

Frequently Asked Questions

Do all small projects need a Des Moines grading permit?
No. Residential in-fill jobs under an acre that stay below the § 42-86(a)(6) area thresholds can skip the licensed-professional plan requirement if the city engineer agrees erosion risk is minimal.
What if the city engineer misses the review deadline?
Under § 42-88(b), failure to act within 15 working days counts as approval of the application as submitted, as long as it doesn't conflict with existing law.

Sources & Official References

Other rules in Des Moines

All Des Moines rules

Compare Des Moines to another location·View the Iowa environmental rules overview

Get notified when Erosion Control in Des Moines, IA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.