Where it applies
250 feet of great ponds and wetlands, 75 feet of streams
Plan required for
Permitted filling, grading or excavation leaving unstabilized soil
Temporary stabilization
Within one week of last active work
Permanent stabilization
Within nine months of initial exposure
Mulch rate
At least one bale per 500 square feet
Fines
$100 to $2500 per violation per day

Summary

Inside Dixmont's shoreland zone, any permitted filling, grading or excavation that leaves soil unstabilized needs a written erosion and sedimentation control plan approved by the permitting authority. Exposed ground must be stabilized within one week of last work and permanently within nine months. Outside the shoreland zone, only nonresidential and multifamily projects under Site Plan Review face a separate erosion standard.

(1) All activities which involve filling, grading, excavation or other similar activities which result in unstabilized soil conditions and which require a permit shall also require a written soil erosion and sedimentation control plan. The plan shall be submitted to the permitting authority for approval and shall include, where applicable, provisions for: ... (4) Any exposed ground area shall be temporarily or permanently stabilized within one (1) week from the time it was last actively worked, by use of riprap, sod, seed, and mulch, or other effective measures. In all cases permanent stabilization shall occur within nine (9) months of the initial date of exposure. ... (5) Natural and man-made drainage ways and drainage outlets shall be protected from erosion from water flowing through them. Drainage ways shall be designed and constructed in order to carry water from a twenty five (25) year storm or greater, and shall be stabilized with vegetation or lined with riprap.

Full Breakdown

The erosion standard sits in Section 15(T) of the Dixmont Shoreland Zoning Ordinance, adopted March 19, 2016. It reaches only land within 250 feet of the normal high-water line of great ponds, 250 feet of the upland edge of a freshwater wetland, and 75 feet of the normal high-water line of a stream. Dixmont has no town-wide zoning ordinance, so a lot outside those distances is not touched by this section.

Inside the zone the trigger is a permit. Any activity that requires a permit and involves filling, grading, excavation or similar work leaving unstabilized soil must come with a written soil erosion and sedimentation control plan, submitted to the permitting authority for approval. Where applicable the plan covers mulching and revegetation of disturbed soil, temporary runoff controls such as hay bales, silt fencing or diversion ditches, and permanent stabilization structures such as retaining walls or riprap. The controls must be in operation during all stages of the activity, and the amount of exposed soil at every phase of construction must be minimized.

The timeline is fixed. Exposed ground must be temporarily or permanently stabilized within one week from the time it was last actively worked, and permanent stabilization must occur within nine months of the initial date of exposure. Mulch is applied at a rate of at least one bale per five hundred square feet and maintained until a catch of vegetation is established. Drainage ways must be designed to carry water from a twenty five year storm or greater and be stabilized with vegetation or lined with riprap.

When an excavation contractor performs the work, a person certified in erosion control practices by the Maine Department of Environmental Protection must manage the controls and be present at the site each day the activities occur. The plan or permit application must list that person's name and certification number.

Nonresidential and multifamily projects reviewed by the Planning Board face a separate standard. Section 9.8 of the Site Plan Review Ordinance requires an active program meeting the most recent edition of the State of Maine Erosion and Sediment Control Handbook for Construction: Best Management Practices.

Violations & Fines

The Code Enforcement Officer enforces Section 15(T) by written notice ordering the action needed to correct the violation. Under Section 16(I)(4), any person, including a landowner, a landowner's agent or a contractor, is penalized under 30-A, M.R.S.A. section 4452. The printed note puts fines at not less than $100 nor more than $2500 per violation for each day the violation continues, and $5000 as the maximum in a resource protection district. Any violation of the Ordinance is deemed a nuisance.

Frequently Asked Questions

Does Dixmont require an erosion control plan for every construction project?
No. Section 15(T) applies inside the shoreland zone, which covers 250 feet from great ponds and freshwater wetlands and 75 feet from streams, and only to activities that need a permit. Nonresidential and multifamily projects under Site Plan Review follow a separate handbook-based standard in Section 9.8 of that ordinance.
How fast must bare soil be stabilized in the shoreland zone?
Exposed ground must be temporarily or permanently stabilized within one week from the time it was last actively worked, using riprap, sod, seed, mulch or other effective measures. Permanent stabilization must follow within nine months of the initial date of exposure. Mulch goes down at a rate of at least one bale per five hundred square feet.
Who supervises erosion controls when an excavation contractor does the job?
A person certified in erosion control practices by the Maine Department of Environmental Protection must be responsible for erosion and sedimentation control practices and be present each day the work occurs. The plan or permit application must include that person's name and certification number.
What are the fines for ignoring the erosion rules?
Violators are penalized under 30-A, M.R.S.A. section 4452. The ordinance's note lists fines of not less than $100 nor more than $2500 per violation for each day the violation continues, and a $5000 maximum in a resource protection district. The Code Enforcement Officer starts enforcement with a written notice.

Sources & Official References

Other rules in Dixmont

All Dixmont rules

Compare Dixmont to another location·View the Maine environmental rules overview

Get notified when Erosion Control in Dixmont, ME changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.