Edmonds, WA Environmental Rules: Erosion Control (2026)
Key Facts
- SWPPP required at
- 2,000 sq ft hard surface or 7,000 sq ft disturbance
- Seasonal restriction
- Oct 1 to Apr 30 clearing/grading limits
- SWPPP elements
- 13 elements per SWMMWW Volume II
- Max civil penalty
- $20,000 per occurrence
- Enforcing agency
- Public Works and Utilities Director
Summary
Edmonds requires a construction stormwater pollution prevention plan (SWPPP) under ECDC 18.30.060(D)(2) for any project adding 2,000 square feet or more of new plus replaced hard surface, disturbing 7,000 square feet or more of land, or demolishing a structure with 2,000 square feet of hard surface. Between October 1 and April 30, the city further restricts clearing and grading unless erosion and sediment controls are demonstrated to hold silt-laden runoff on site.
A construction SWPPP is required for all projects which (A) result in 2,000 square feet or more of new plus replaced hard surface area, (B) where a structure with an exterior hard surface area of at least 2,000 square feet is being demolished, (C) which disturb 7,000 square feet or more of land, or (D) when the site falls within the earth subsidence landslide hazard area, landslide hazard area or steep slope critical area. ... Seasonal Work Limitations. From October 1st through April 30th, clearing, grading, and other soil disturbing activities may only be authorized by the city if it can be demonstrated that silt-laden runoff will be prevented from leaving the site through a combination of the following: i. Site conditions including existing vegetative coverage, slope, soil type, and proximity to receiving waters; and ii. Limitations on activities and the extent of disturbed areas; and iii. Proposed erosion and sediment control measures, in accordance with subsection (D)(2)(d) of this section.
Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 4444, passed August 3, 2026).
Full Breakdown
Under Minimum Requirement No. 2 of the city's stormwater chapter, every development project is responsible for preventing erosion and the discharge of sediment and other pollutants into receiving waters; a site already covered by the Department of Ecology's general NPDES construction stormwater permit and complying with it satisfies this requirement. A written construction SWPPP with a narrative and drawings is required whenever a project adds 2,000 square feet or more of new plus replaced hard surface, demolishes a structure with at least 2,000 square feet of exterior hard surface, disturbs 7,000 square feet or more of land, or sits within an earth subsidence landslide hazard area, landslide hazard area, or steep slope critical area.
The SWPPP must address 13 required elements consistent with Volume II of the state's 2019 Stormwater Management Manual for Western Washington, and it must be implemented from initial land disturbance through final stabilization. Even projects below those thresholds must still consider all 13 SWPPP elements and put controls in place for any that apply. The city imposes an additional seasonal limitation: from October 1st through April 30th, clearing, grading, and other soil-disturbing work may only proceed if the applicant demonstrates, based on site conditions such as vegetative cover, slope, soil type, and proximity to receiving waters, that silt-laden runoff will be kept on site through limited disturbed areas and approved erosion and sediment control measures.
The city may expand or restrict this seasonal window based on local weather. Routine maintenance of existing erosion and sediment control BMPs and public utility work that does not expose soil are exempt from the seasonal limits, but earth subsidence and landslide hazard area sites are not.
Violations & Fines
Erosion control violations are enforced under the same Chapter 18.30 civil penalty scheme: the director can order corrective action, and continued noncompliance brings a civil penalty under Chapter 20.110 ECDC that the hearing examiner may set up to $20,000 per occurrence, weighing risk to public health, environmental and property damage, and any economic benefit gained by skipping controls. Unresolved violations escalate to 150 percent, then 200 percent of the initial penalty in successive 15-day periods.
Frequently Asked Questions
Do I need an erosion control plan for a small addition in Edmonds?
Can I clear and grade a lot in Edmonds during the winter?
What triggers a mandatory construction SWPPP in Edmonds?
Sources & Official References
Other rules in Edmonds
Compare Edmonds to another location·View the Washington environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Erosion Control in Nearby Cities
How other cities in Snohomish County handle erosion control.