Marysville, WA Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Fill/excavation trigger
50 cubic yards combined
Clearing trigger
over 1,000 sq ft
Issued by
city engineering department
Permit term
1 year, extendable 1 year

Summary

Marysville requires a clearing and grading permit before moving 50 or more cubic yards of fill and cut, clearing over 1,000 square feet, or disturbing a sensitive area, issued by engineering for one year.

A clearing and grading permit is required for a project involving any of the following, except as provided for in subsection (2) of this section. ... Fill and/or excavation totaling 50 cubic yards. ... Over 1,000 square feet of clearing, as measured at the ground level. ... The clearing and grading permit shall be issued by the engineering department and shall be effective for one year but may, with cause shown, be extended for an additional one-year period.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4922912; v1 updated 2026-06-08; through 06-08-2026).

Full Breakdown

A clearing and grading permit is required whenever a project involves clearing or excavation in an environmentally sensitive area or buffer, totals 50 or more cubic yards of combined fill and excavation, or clears more than 1,000 square feet at ground level. Exemptions cover agricultural management of existing farmed areas, routine landscape maintenance, emergency work to correct an immediate danger, cemetery graves, and city engineer-approved isolated work with no danger to property. The permit is issued by the engineering department, is valid for one year, and can be extended one additional year for cause; the review fee is set in MMC § 14.07.005.

Violations & Fines

Projects that exceed the fill, excavation, or clearing thresholds without an approved permit are subject to city enforcement and stop-work action; permits that lapse after their one-year term without an extension must be reapplied for before work continues.

Frequently Asked Questions

When does Marysville require a grading permit?
When a project moves 50 or more cubic yards of combined fill and excavation, clears over 1,000 square feet, or disturbs an environmentally sensitive area or its buffer.
How long is a Marysville grading permit valid?
One year from issuance by the engineering department, with a one-year extension available if the applicant shows cause.

Sources & Official References

Other rules in Marysville

All Marysville rules

Compare Marysville to another location·View the Washington environmental rules overview

Get notified when Erosion Control in Marysville, WA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Snohomish County handle erosion control.

Edmonds, WA
Some Restrictions
Lynnwood, WA
Some Restrictions
Everett, WA
Some Restrictions