Elizabeth, NJ Environmental Rules: Erosion Control (2026)
Key Facts
- Erosion standard source
- NJ Soil and Sediment Control Act, N.J.S.A. 4:24-39
- Implementing rules
- N.J.A.C. 2:90
- Minor development rule
- No erosion increase on or off site
- Review path
- Site stormwater plan to board, engineer or zoning officer
- Max penalty
- $2,000 fine plus $1,250 repeat-offense fine
Summary
Elizabeth ties construction-site erosion control to New Jersey's own minimum standard: Section 13.24.030 requires every major development's stormwater measures to meet the erosion-control minimums set by the state's Soil and Sediment Control Act and its implementing rules, alongside groundwater recharge and runoff quality and quantity controls, while smaller minor developments must independently avoid increasing erosion on or off the site.
Stormwater management measures for major development shall be designed to provide erosion control, groundwater recharge, stormwater runoff quantity control, and stormwater runoff quality treatment as follows:1.The minimum standards for erosion control are those established under the Soil and Sediment Control Act, N.J.S.A. 4:24-39 et seq., and implementing rules at N.J.A.C. 2:90.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 31).
Full Breakdown
24 (Stormwater Management) as rewritten by Ordinance No. 6014 on June 25, 2024, sets erosion control as one of four design standards every major development's stormwater measures must satisfy, alongside groundwater recharge, runoff quantity control and runoff quality treatment. A. C. 2:90, govern what erosion-control measures a major development site must install during construction. 110(C) sets a separate but related rule: no minor development may cause an increase in erosion on site or off site, and any downspout or area drain serving an impervious surface must discharge to a pervious surface or an approved stormwater best-management practice, unless the city engineer approves otherwise.
110(C)(4) additionally requires soil erosion and sediment control measures on minor development sites to follow the Standards for Soil Erosion and Sediment Control in New Jersey, the state's technical manual for construction-phase practices like silt fencing, inlet protection and stabilized construction entrances. 110(B) must demonstrate compliance with these erosion-control references before any building or grading permit tied to the project can proceed.
Violations & Fines
Erosion control violations under Chapter 13.24 draw the same penalty whether tied to a major or minor development: Section 13.24.120, applied to minor developments through Section 13.24.110(E), sets a fine of not more than $2,000, up to ninety days in the Union County Jail, or up to ninety days of community service, with an added fine of up to $1,250 for a repeat conviction within one year.
Frequently Asked Questions
What erosion-control standard applies to construction sites in Elizabeth?
Do smaller residential projects in Elizabeth have erosion control rules too?
What's the penalty for an erosion control violation on an Elizabeth construction site?
Sources & Official References
Other rules in Elizabeth
Compare Elizabeth to another location·View the New Jersey environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.