Key Facts

Sediment reduction target
80% total suspended solids
Plan required
written, site-specific, per Sec. 16-41
Duration
until final site stabilization
Enforcement
stop-work order authority
Penalty
$50–$500 forfeiture per day

Summary

Green Bay requires permitted construction sites to cut sediment-laden runoff by 80 percent under an approved erosion and sediment control plan before the site reaches final stabilization.

(1)BMPs shall be designed, installed, inspected and maintained to control total suspended solids carried in runoff from the construction site as follows:a.For permitted construction sites of land disturbing construction activity, reduce the total suspended solids load by 80 percent, on an average annual basis, as compared with no sediment or erosion controls until the construction site has undergone final stabilization. No person shall be required to exceed an 80 percent sediment reduction to meet the requirements of this subsection.

Full Breakdown

City Code § 16-39 sets the erosion and sediment control performance standard for construction sites that require a permit under Article II. The responsible party must implement a written, site-specific erosion and sediment control plan meeting Sec. 16-41, using BMPs designed to reduce the total suspended solids carried in runoff from the site by 80 percent on an average annual basis, compared to having no controls at all, until the site reaches final stabilization. No one is required to exceed the 80 percent reduction target, and BMPs may be combined to reach it; if the target isn't achievable, the plan must explain why in writing.

Violations & Fines

Violating any provision of this article draws a forfeiture of $50.00 to $500.00 plus costs of prosecution per offense, with each day of noncompliance a separate violation (Sec. 16-44(a)(6)); the City may also issue a stop-work order.

Frequently Asked Questions

Does every construction site in Green Bay need an erosion control plan?
Only permitted sites under Sec. 16-39: smaller sites not requiring a permit follow the lighter standard in Sec. 16-38 instead.
What sediment reduction does Green Bay require during construction?
BMPs must cut the total suspended solids load in runoff by 80 percent on an average annual basis until the site is fully stabilized, per Sec. 16-39(c)(1)a.

Sources & Official References

Other rules in Green Bay

All Green Bay rules

Compare Green Bay to another location·View the Wisconsin environmental rules overview

Get notified when Erosion Control in Green Bay, WI changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Brown County handle erosion control.

De Pere, WI
Some Restrictions
Ashwaubenon, WI
Some Restrictions