Trigger
1+ acre land disturbance projects
Required with
Stormwater management permit application
Design standard
Massachusetts Stormwater Handbook
Reviewing official
DPW Director
Enforcement track
Same as Ch. 219 SMP violations

Summary

Anyone applying for a stormwater management permit in the City of Haverhill for a construction project disturbing an acre or more must submit an erosion and sedimentation control plan as part of the application package, under City Code § 219-8B. Design must also meet Massachusetts Stormwater Standards for sediment and erosion control under § 219-9.

Applications for an SMP shall include the materials as specified in this section. ... The SMP application package shall include: ... A completed application form with original signatures of all owners; ... A list of abutters; ... Payment of the application and review fees; ... Stormwater management plan; ... Erosion and sedimentation control plan; and ... Operation and maintenance plan. ... At a minimum, the selection, design and construction of all pre-treatment, treatment and infiltration BMPs shall be in accordance with the latest edition of the Massachusetts Stormwater Handbook and shall be consistent with all elements of the Massachusetts Stormwater Standards including but not limited to those regarding new stormwater conveyances, peak runoff rates, recharge, land uses with higher potential pollutant loads, discharges to Zone II or interim wellhead protection areas, sediment and erosion control, and illicit discharges.

Full Breakdown

Chapter 219, Stormwater Management, folds erosion and sediment control into the stormwater management permit (SMP) process rather than treating it as a stand-alone chapter. Section 219-8B lists what an SMP application to the Director of the Department of Public Works must include: a completed application form signed by all owners, a list of abutters, the application and review fees, a stormwater management plan, an erosion and sedimentation control plan, and an operation and maintenance plan. The chapter defines an 'erosion and sedimentation control plan' as a plan showing the location and construction detail of the erosion and sediment reduction controls to be used on a construction site.

Design standards for those controls are set by § 219-9, which requires that selection, design and construction of BMPs be consistent with the latest Massachusetts Stormwater Handbook and Stormwater Management Standards, explicitly covering sediment and erosion control alongside peak runoff rates, recharge and pollutant loading. Because the SMP applies to land disturbance of one acre or more (or smaller phases of a larger common plan totaling an acre), a construction project below that acre threshold is not required to file an erosion and sedimentation control plan under this chapter unless it falls under one of the other regulated triggers in § 219-6.

The Director can request additional information, condition approval on specific control measures, or disapprove an application that does not meet these requirements under § 219-8D, and enforcement of an approved plan runs through the same notice-of-violation and penalty structure in §§ 219-16 and 219-19 that governs the rest of Chapter 219.

Violations & Fines

Failure to submit or follow an approved erosion and sedimentation control plan is enforced as a stormwater management permit violation. The Director of Public Works can issue a notice of violation under § 219-16 ordering remediation, and penalties follow the noncriminal disposition schedule in § 219-19: a written warning for the first offense, escalating to $50, $100, and $150 for later offenses, each day counted separately.

Frequently Asked Questions

Does Haverhill require a separate erosion control permit?
No. An erosion and sedimentation control plan is submitted as one component of the stormwater management permit application required by § 219-8B for projects that disturb an acre or more of land.
What must an erosion control plan show in Haverhill?
Chapter 219 defines it as a plan showing the location and construction detail of the erosion and sediment reduction controls to be used on the construction site, reviewed by the Department of Public Works Director.
What design standard applies to erosion controls in Haverhill?
Section 219-9 requires BMP selection, design and construction to follow the latest Massachusetts Stormwater Handbook and Stormwater Management Standards, which specifically address sediment and erosion control.

Sources & Official References

Other rules in Haverhill

All Haverhill rules

Compare Haverhill to another location·View the Massachusetts environmental rules overview

Get notified when Erosion Control in Haverhill, MA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.