Key Facts

Grading permit gate
Disturbed area of five acres or greater: NOI and SWPPP
Coverage window
Demolition or start of construction until certificate of occupancy
Off-site sediment
Removed the same day it leaves the site
Soil piles
Covered until used or removed
Enforcement
Infraction, each day a separate offense
Inspections
On consent or with an inspection warrant

Summary

In the City of Huntington Park, California, Municipal Code § 7-9.09 requires every construction project to keep sediment and construction waste on site from demolition until the certificate of occupancy. Developments disturbing five acres or greater need a state stormwater notice of intent and a SWPPP before a grading permit issues.

§ 7-9.09. Requirements for construction projects. (a) No grading permit shall be issued for developments with disturbed areas of five acres or greater unless the applicant can show that: (1) a notice of intent (NOI) to comply with the State Construction Activity Storm Water Permit has been filed; and (2) a Storm Water Pollution Prevention Plan (SWPPP) has been prepared. (b) The following requirements shall apply to all projects undergoing construction in the City. The requirements set forth below shall apply at the time of demolition of an existing structure or commencement of construction and until receipt of a certificate of occupancy: (1) Sediment, construction waste and other pollutants from construction sites and parking areas, including runoff from equipment and vehicle washing at construction sites, shall be retained on the site to the maximum extent practicable. (2) Any sediments or other materials which are not retained on the site shall be removed the same day as they leave the site. ... a temporary sediment barrier shall be installed.

Full Breakdown

Section 7-9.09 sits in Chapter 7-9, Stormwater Management and Discharge, of the Huntington Park Municipal Code and applies to all projects undergoing construction in the City of Huntington Park, Los Angeles County.

Subsection (a) is a grading permit gate. No grading permit issues for developments with disturbed areas of five acres or greater unless the applicant shows that a notice of intent to comply with the State Construction Activity Storm Water Permit has been filed and a Storm Water Pollution Prevention Plan has been prepared.

Subsection (b) runs from demolition of an existing structure or commencement of construction until receipt of a certificate of occupancy. During that window, sediment, construction waste and other pollutants, including runoff from equipment and vehicle washing, must stay on the site to the maximum extent practicable. Anything that leaves the site must be removed the same day, and the City Engineer and/or Building Official can require a temporary sediment barrier. Plastic covering is allowed on an emergency basis only, paired with runoff devices that intercept and safely convey the runoff. Excavated soil must be placed to minimize sediment running into the street or onto adjoining properties, and soil piles stay covered until the soil is used or removed. Washing construction or other industrial vehicles adjacent to a construction site is prohibited. Drainage controls are required as needed for the grading and topography, and the listed options are detention ponds, sediment ponds, infiltration pits, dikes, filter berms, ditches, down drains, chutes and flumes.

Subsection (c) lets the City condition a construction permit on reasonable limits on clearing of vegetation, including how long soil can stay bare and, in certain sensitive cases, a ban on bare soil. Subsection (d) points owners and developers to the Construction Best Management Practices Handbook published by the Storm Water Quality Task Force. Fees for plan checking and monitoring are set by City Council resolution under § 7-9.10.

Violations & Fines

A violation of § 7-9.09 is an infraction punishable as provided in § 1-2.01, and each day a violation occurs is a separate offense. Section 1-2.01 sets infraction fines at $50 for a first conviction, $100 for a second within one year, and $250 for a third or later within one year, unless the Code or a Council resolution provides otherwise. Under subsection (h) the violation is a public nuisance and the City Attorney is authorized to abate it by civil action. Penalties and remedies are cumulative.

Frequently Asked Questions

When must a project in the City of Huntington Park file a SWPPP?
Under § 7-9.09(a), no grading permit issues for a development with disturbed areas of five acres or greater unless the applicant shows that a notice of intent under the State Construction Activity Storm Water Permit has been filed and a SWPPP has been prepared. Smaller projects still follow the subsection (b) site rules.
How fast must sediment that leaves a Huntington Park construction site be cleaned up?
Sediments or other materials not retained on the site must be removed the same day as they leave the site, per § 7-9.09(b)(2). Where the City Engineer and/or Building Official finds it necessary, a temporary sediment barrier must also be installed. Soil piles must be covered until the soil is used or removed.
Can contractors wash trucks next to the site?
No. Section 7-9.09(b)(5) prohibits washing of construction or other industrial vehicles adjacent to a construction site and bars any water from washing vehicles on a construction site from running off into the City's storm drain system. Equipment and vehicle wash runoff is also covered by the on-site retention rule in (b)(1).
Can the City limit how long soil stays bare?
Yes. Section 7-9.09(c) allows the City, as a condition of granting a construction permit, to set reasonable limits on the clearing of vegetation, including regulating the length of time during which soil can be bare and, in certain sensitive cases, prohibiting bare soil.

Sources & Official References

Other rules in Huntington Park

All Huntington Park rules

California rules heatmap·Compare Huntington Park to another location·View the California environmental rules overview

Get notified when Erosion Control in Huntington Park, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Los Angeles County handle erosion control.

Carson, CA
Some Restrictions
West Covina, CA
Some Restrictions
El Monte, CA
Some Restrictions
Inglewood, CA
Some Restrictions
Santa Monica, CA
Some Restrictions
South Gate, CA
Some Restrictions
Santa Clarita, CA
Some Restrictions
Palmdale, CA
Some Restrictions