Key Facts

Plan trigger
Disturbing more than 1/2 acre
Filing lead time
30 days before work begins
Stabilization deadline
21 days after grading phase
Max civil penalty
$5,000 per day
Criminal exposure
Class 2 misdemeanor, up to $5,000 fine
Governing section
Town Code § 153.071

Summary

In the Town of Kill Devil Hills, North Carolina, disturbing more than half an acre of land requires a town-approved erosion and sedimentation control plan filed at least 30 days ahead of work, and violations carry civil penalties up to $5,000 per day plus possible criminal misdemeanor charges.

(1) No person shall initiate any land-disturbing activity which uncovers more than 1/2 acre without having an erosion control plan approved by the town. ... (a) Civil penalty for a violation. Any person who violates any of the provisions of this section ... is subject to a civil penalty. The maximum civil penalty that the town may assess is $5,000. ... Each day of a continuing violation shall constitute a separate violation.

Full Breakdown

071 SOIL EROSION AND SEDIMENTATION CONTROL applies townwide to regulated land-disturbing activity, with limited exclusions for agricultural production, forestry conducted under state Forest Practice Guidelines, mining-act permitted activity and a few federal wetlands-restoration categories. 071(D) require a buffer along any lake or natural watercourse sufficient to confine visible siltation within 25% of the buffer nearer the disturbed area, cap graded slope angles to what vegetative cover or erosion-control devices can retain, require exposed slopes to be planted or stabilized within 21 days of any grading phase, and require permanent ground cover after construction within 15 working days or 90 calendar days, whichever is shorter.

071(R)(1)(a) sets a civil penalty of up to $5,000 per violation, with each day of a continuing violation constituting a separate violation, and a single non-continuing $5,000 civil penalty applies to anyone who simply fails to file a required plan. § 113A-64, punishable by a fine up to $5,000. 071(R)(1)(d)-(f). 071(T).

Violations & Fines

Initiating land-disturbing activity over half an acre without an approved erosion control plan, or failing to follow an approved plan's terms, exposes the responsible party to a civil penalty of up to $5,000 per day under § 153.071(R)(1)(a), and a knowing or willful violation is a Class 2 misdemeanor under § 153.071(R)(2) carrying a fine up to $5,000 per G.S. § 113A-64; the town may also pursue injunctive relief in Dare County Superior Court and require restoration of any waters or land damaged by sedimentation.

Frequently Asked Questions

When does a construction project in Kill Devil Hills need an erosion control plan?
Section 153.071(C)(1) requires an approved erosion control plan for any land-disturbing activity uncovering more than half an acre. Under § 153.071(E)(1), that plan must be filed with the town and the Dare County Soil and Water Conservation District at least 30 days before work starts.
How quickly must exposed slopes be stabilized during construction in Kill Devil Hills?
Section 153.071(D)(2) requires slopes left exposed by grading to be planted or otherwise given ground cover or erosion control devices within 21 days of any grading phase, and permanent ground cover must be established within 15 working days or 90 calendar days of completing construction, whichever is shorter.
What are the penalties for violating Kill Devil Hills' erosion control ordinance?
Section 153.071(R) sets a civil penalty up to $5,000, with each day of a continuing violation counted separately, and a $5,000 penalty just for failing to file a required plan. A knowing or willful violation is also a Class 2 misdemeanor under state law, punishable by a fine up to $5,000.

Sources & Official References

Other rules in Kill Devil Hills

All Kill Devil Hills rules

Compare Kill Devil Hills to another location·View the North Carolina environmental rules overview

Get notified when Erosion Control in Kill Devil Hills, NC changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.