Key Facts

Governing section
Logan Municipal Code § 13.14.260
Plan standard
Must meet the Utah general construction permit
Certification
Utah-licensed engineer unless city engineer waives it
Street cleanup deadline
End of the workday, by machine, broom or shovel
Permit trigger
One or more acres, or a larger common plan
Permit expiry
180 days to start, 18 months to finish
Penalty
Class B misdemeanor or administrative enforcement

Summary

In Logan City, Utah, construction activities regulated by the stormwater chapter need a sediment and erosion control plan that meets the Utah general construction permit. Section 13.14.260 requires an engineer's certification unless the city engineer waives it, and sediment tracked onto streets must be removed by the end of the workday.

The applicant must prepare a sediment and erosion control plan which meets the requirement of the state of Utah general construction permit for all construction activities regulated by this chapter. A. The sediment and erosion control plan shall accurately describe the potential for soil erosion and sedimentation problems resulting from land disturbing activity and shall explain and illustrate the measures that are to be taken to control these problems. ... The plan shall be certified by a registered professional engineer licensed in the state of Utah, unless it is determined by the city engineer that said certification is not necessary because of the simplicity or the common nature of the plan. ... 15. Specific details for the construction of rock pads, wash down pads, and settling basins for controlling erosion; ... Soil, sediment, and debris brought onto streets and public ways must be removed by the end of the workday by machine, broom or shovel as a minimum. ... Failure to remove the sediment, soil or debris shall be deemed a violation of this chapter.

Full Breakdown

Logan Municipal Code § 13.14.260 requires the applicant to prepare a sediment and erosion control plan for all construction activities regulated by chapter 13.14. The plan has to describe the potential for soil erosion and sedimentation from the land disturbing activity and explain and illustrate the control measures. Its length and complexity scale with the size of the project, the severity of the site condition and the potential for off site damage. A registered professional engineer licensed in Utah certifies the plan unless the city engineer decides certification is unnecessary because of the simplicity or common nature of the plan. The plan must also follow the BMP manual.

The code lists 17 minimum contents, among them a project description, a topographic map with contour intervals, existing drainageways and floodplains, tree protection measures, limits of clearing, grading and filling, flows leaving the site during and after construction, the projected sequence of work, detailed drawings of temporary and permanent stabilization, a maintenance schedule, and details for rock pads, wash down pads and settling basins. Mud and debris on public streets must be removed by the end of the workday by machine, broom or shovel as a minimum, and the city engineer can order more frequent cleaning.

The plan feeds the permit. Under § 13.14.090 a land disturbance permit from the city engineer is required for activity that disturbs one or more acres, for smaller activity that is part of a larger common plan affecting one or more acre, and for any smaller activity the city engineer finds poses a unique threat. Section 13.14.110 bars a building permit until the land disturbance permit is obtained. The city engineer answers a complete application within fifteen (15) days (§ 13.14.140). A permit expires if substantial work has not begun within 180 calendar days or is not complete within 18 months, and an extension for good cause cannot exceed six months (§ 13.14.150). The applicant gives the city engineer ten working days notice before construction starts (§ 13.14.160).

Violations & Fines

Failure to remove sediment, soil or debris from streets and public ways is expressly deemed a violation of the chapter. Any violation of chapter 13.14 or of a permit issued under it is punishable as a class B misdemeanor, with administrative enforcement under LDC section 17.60 as an alternative (§ 13.14.470). The city engineer can issue notices of violation, stop work orders and citations (§ 13.14.450), and the city can recover its damages and enforcement costs (§ 13.14.480).

Frequently Asked Questions

When does a Logan project need a land disturbance permit?
Section 13.14.090 requires one for land disturbing activity of one or more acres, for smaller activity that is part of a larger common plan affecting one or more acre, and for smaller activity the city engineer finds poses a unique threat. Borrow pits, parking lots, fill stockpiling and development of any parcel are also listed.
Does my erosion control plan need an engineer's stamp in Logan?
Section 13.14.260 says the plan shall be certified by a registered professional engineer licensed in Utah. The one exception is a determination by the city engineer that certification is not necessary because of the simplicity or common nature of the plan. The plan must also conform to the BMP manual.
How fast must I clean mud off the street after hauling in Logan?
Soil, sediment and debris brought onto streets and public ways must be removed by the end of the workday by machine, broom or shovel as a minimum. The city engineer can direct more frequent cleaning if hazards or tracking nuisances are present, and failure to remove the material is a violation.
How long does a Logan land disturbance permit last?
Under § 13.14.150 the permit becomes null and void if substantial work has not commenced within 180 calendar days of issuance, or if the work is not complete within 18 months of the start of construction. The city engineer can grant a written extension for good cause, capped at six months, if requested before expiration.

Sources & Official References

Other rules in Logan

All Logan rules

Compare Logan to another location·View the Utah environmental rules overview

Get notified when Erosion Control in Logan, UT changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.