Snohomish County, WA Environmental Rules: Erosion Control (2026)
Key Facts
- Governing section
- SCC 30.63A.450
- Applies to
- All new development/redevelopment, any size
- Wet-season limitation
- October 1 to April 30
- Trigger for corrective action
- Turbid water leaving the site
- Exemptions
- 100% on-site infiltration; routine BMP repair; utility maintenance
- Enforcing agency
- Snohomish County Public Works
Summary
Unincorporated Snohomish County requires every new development and redevelopment project, regardless of size, to control soil erosion and sediment discharge into receiving waters through a Stormwater Pollution Prevention Plan (SWPPP) approved before construction begins.
(2) Applicants for all new development and redevelopment projects of any size shall be responsible for preventing soil erosion and the discharge of sediment and pollutants into receiving waters. A SWPPP must be submitted as part of the stormwater site plan. The SWPPP shall be implemented prior to initial soil disturbance through final stabilization. ... (4) All new development and redevelopment shall be designed to prevent erosion and discharge of sediment and other pollutants into receiving waters. If erosion and sediment control requirements are not met (i.e. turbid water is leaving the site), then the department shall require that the contractor maintain the existing BMPs or implement other BMPs as appropriate. (5) To control sediment transport and erosion during the wet season from October 1st through April 30th, seasonal work limitations shall apply, except as otherwise exempt per subsection (6) of this section.
Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through legislation passed August 12, 2026).
Full Breakdown
450 makes the applicant for any new development or redevelopment project responsible for preventing soil erosion and the discharge of sediment and pollutants into receiving waters, no matter the project's size. A SWPPP must be submitted as part of the stormwater site plan, with a narrative and drawings describing when and where erosion and sediment control best management practices (BMPs) will be installed, the performance expected, and the corrective actions if that performance is not met. The SWPPP must be implemented before initial soil disturbance and stay in effect through final stabilization of the site.
During the wet season, from October 1 through April 30, the county imposes seasonal work limitations on land-disturbing activity: work is allowed only if the applicant demonstrates to the Snohomish County Department of Public Works' satisfaction that turbid water will be kept from leaving the site, based on existing vegetative cover, slope, soil type, proximity to receiving waters, limits on the extent of disturbed area, and the proposed erosion and sediment control measures. The county's Drainage Manual, incorporated by reference, sets the specific BMP design standards used to meet these requirements.
If turbid water is found leaving a site because erosion and sediment controls are not being met, the department can order the contractor to maintain the BMPs already installed or add new ones. Three narrow activities are exempt from the wet-season limitation: sites where stormwater runoff achieves 100 percent on-site infiltration into approved, installed facilities; routine maintenance and necessary repair of existing erosion and sediment control BMPs; and routine maintenance of public facilities or utility structures that does not expose soil or strip vegetative cover.
The section was most recently amended by Ordinance 26-021 (June 17, 2026, effective July 1, 2026), following earlier amendments in 2010, 2016 and 2021 that reorganized the SWPPP element sections referenced in this part of the chapter.
Violations & Fines
Enforcement runs through the Snohomish County Department of Public Works (Surface Water Management). Inspectors treat turbid water leaving a construction site as evidence the SWPPP's erosion and sediment controls have failed, and can order the contractor to maintain existing BMPs or install additional ones on the spot. Continuing land-disturbing work during the October 1 through April 30 wet season without meeting the seasonal limitation showing, or without a qualifying exemption, is a code violation subject to stop-work action and correction under the county's Drainage Manual standards.
Frequently Asked Questions
Does every construction project in unincorporated Snohomish County need an erosion control plan?
Can I clear or grade land in the winter in Snohomish County?
What happens if my site is discharging muddy water during construction?
Sources & Official References
Other rules in Snohomish County
Compare Snohomish County to another location·View the Washington environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.