Minnetonka, MN Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified October 2026

Key Facts

Permit trigger
5,000 square feet of exposed soil or 50 cubic yards moved
Idle stabilization
Exposed soil stabilized if not worked for 14 days
Inspections
Erosion and sediment controls inspected weekly and maintained
Sediment removal
When it reaches 1/3 of the designed capacity
Financial security
Not to exceed 150% of estimated cost, or 125% of an actual bid
Created slopes
Not steeper than 3:1, with limited 2:1 exceptions

Summary

In the City of Minnetonka, Minnesota (Hennepin County), the Minnetonka City Council requires a grading and erosion control plan for land-disturbing work, and section 300.28 subdivision 17 sets the field rules: exposed soil stabilized after 14 days without work, storm drain inlets protected, weekly inspections, and sediment removed at 1/3 of designed capacity.

a) All plans must be consistent with the Minnesota Pollution Control Agency's construction general permit as applicable. b) Except as otherwise provided by the city planner, a grading and erosion control plan and the work conducted under an approved plan must comply with all of the following requirements as applicable: 1) The work must be scheduled so as to minimize the amount of soil exposed at any one time. Land disturbance and removal of existing vegetation must be minimized to avoid adverse impacts to adjacent properties and natural resources. All exposed soil must be stabilized as soon as possible if the exposed soil has not been worked for 14 days. ... 7) Tree protection or construction fence must be installed to minimize impacts to the critical root zones of adjacent trees or to prevent impacts to adjacent properties. ... 10) All erosion and sediment control and tree and wetland protection measures must be inspected on a weekly basis and maintained. Sediment must be removed from these measures when it accumulates to a depth of 1/3 of the designed capacity. 11) All storm drain inlets must be protected during construction.

Full Breakdown

Section 300.28 subdivision 15 of the Minnetonka City Code requires a grading permit for excavating, grading, filling or other land-disturbing activity that exposes soil in an area or areas encompassing at least 5,000 square feet or moves at least 50 cubic yards of material. A permit is also required for any such work on a steep slope, wetland, floodplain or shoreland, and for work that de-stabilizes soil or creates the potential for erosion onto property not in common ownership or into a water resource. A grading and erosion control plan goes to the city for approval with any grading permit, preliminary plat, site plan review, lot division, wetland or floodplain alteration permit, and any building permit that involves land-disturbing activity.

Subdivision 16 sets the application. It goes to the city planner with the permit fee from section 710 and a plan covering grades at two foot contour intervals, drainage, a tree survey, a stormwater pollution prevention plan, soil stockpile locations, a construction management plan and a site maintenance inspection schedule naming the person responsible. The city requires a cash deposit or letter of credit not to exceed 150% of the estimated cost of the work, or 125% of an actual bid, and a signed agreement that the city can use the security to correct violations within 48 hours of written notification. Sites disturbing one acre or more also need an inspector deposit. The permit is not approved until all erosion control, tree protection and construction limit measures have been installed and inspected by the city.

Subdivision 17 carries the working rules. Plans must be consistent with the Minnesota Pollution Control Agency construction general permit. Exposed soil is stabilized if not worked for 14 days. Rock construction driveways go where vehicles enter and exit, and streets are swept whenever sediment is tracked. Silt fence goes along the downslope and sideslope perimeters of the grading limits. Pipe outlets need energy dissipation within 24 hours of connection to a surface water. Slopes that are created may not be steeper than 3:1, with narrow exceptions up to 2:1 approved by the city engineer. When one or more acres drains to a common location, a temporary sediment basin is required.

Violations & Fines

Under section 300.03 subdivision 2, a chapter 3 violation is a misdemeanor and each day is a separate offense. A violator of a section 300.28 performance standard must reimburse the city for the actual cost of tests and measurements and pay twice the section 710 fee on any related application. The city can draw on the financial security to correct violations within 48 hours of written notice. A truck tracking mud onto a street is a nuisance under section 845.010, item 11.

Frequently Asked Questions

When do I need a grading permit in Minnetonka?
Section 300.28 subdivision 15(b) requires one for land-disturbing activity that exposes soil in at least 5,000 square feet or moves at least 50 cubic yards of material, and for any such work on a steep slope, wetland, floodplain or shoreland. A separate permit is not required when the work follows a plan approved with a building permit.
How often must erosion controls be inspected?
Weekly. Subdivision 17(b)(10) requires all erosion and sediment control and tree and wetland protection measures to be inspected on a weekly basis and maintained, with sediment removed when it reaches a depth of 1/3 of the designed capacity. The city can also require a written site maintenance inspection log recording each inspection and any corrective work.
How much security does the city hold?
Subdivision 16 sets a cash deposit or letter of credit not to exceed 150% of the estimated cost of the work, or 125% of an actual bid. A separate deposit not to exceed 150% of estimated cost covers street repairs from earth hauling. The applicant also signs an agreement letting the city use the security to correct violations within 48 hours of written notification.
What must be protected on site during construction?
All storm drain inlets must be protected during construction under subdivision 17(b)(11). Tree protection or construction fence must go up to protect the critical root zones of adjacent trees, and silt fence or an equivalent control is required along downslope and sideslope perimeters. Temporary stockpiles cannot sit in natural buffers, surface waters or drainage patterns.

Sources & Official References

Other rules in Minnetonka

All Minnetonka rules

Compare Minnetonka to another location·View the Minnesota environmental rules overview

Get notified when Erosion Control in Minnetonka, MN changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.