Mission, TX Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
Sec. 114-353, City Code
SWP3 threshold
Sites over 1 acre disturbed
Stabilization deadline
14 days after work stops
Sediment basin size
3,600 cu ft per acre
Penalty
Misdemeanor; each day separate offense

Summary

Construction sites in Mission must control erosion and sediment through a stormwater pollution prevention plan, silt fences, sediment basins, and site stabilization within 14 days of work stopping.

For construction sites that will disturb less than one acre of land, the following provisions apply: ... Construction site operators are responsible for retaining all soil and sediment on-site and off of adjacent properties and the public right-of-way. This includes dust control and control of vehicle tracking of dirt off-site. ... Soil and sediment that leaves the construction site must be cleaned-up daily.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 31).

Full Breakdown

Mission's Chapter 114, Article VIII requires every construction site operator to control erosion and sediment, not just projects with state stormwater permits. Sites disturbing less than one acre skip the formal plan but must still retain all soil and sediment on-site, control dust and vehicle tracking, and clean up any escaped sediment daily. Larger sites needing a building or site development permit must submit a stormwater pollution prevention plan (SWP3) with erosion controls like silt fences, sediment traps, or sediment basins sized for a two-year, 24-hour storm. Stabilization measures, temporary or permanent vegetation, mulching, or geotextiles, must start within 14 days after grading stops in any area.

Violations & Fines

Violating the erosion-control rules is a misdemeanor, with each day of noncompliance a separate offense; the city can post a noncompliance flag and issue a stop-work order.

Frequently Asked Questions

Does a small residential construction project need a stormwater plan?
No: sites disturbing less than one acre skip the formal SWP3, but must still retain all soil and sediment on-site, control dust and tracking, and clean up escaped sediment daily.
How fast must bare soil be stabilized after grading stops?
Within 14 days of when construction activity temporarily or permanently ceases on that part of the site, per Sec. 114-353.
What happens if a site ignores an erosion-control violation notice?
The city posts a noncompliance flag, and if uncorrected within three more days, issues a stop-work order halting all activity and further permits.

Sources & Official References

Other rules in Mission

All Mission rules

Texas rules heatmap·Compare Mission to another location·View the Texas environmental rules overview

Get notified when Erosion Control in Mission, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.