Key Facts

SWP3 required
Before building/site development permit
Small sites (<1 acre)
Must retain soil/sediment on-site
Large sites (5+ acres)
Submit NOI copy to city
Sediment basin trigger
10+ disturbed acres, if feasible
Inspection frequency
Every 14 days minimum

Summary

Edinburg requires a stormwater pollution prevention plan before issuing a building or site development permit for any construction that disturbs soil, with mandatory erosion and sediment controls on-site.

The intent of this division is to implement and enforce a program to reduce pollutants in stormwater runoff from construction activities (new development and redevelopment) to the city's MS4. All construction site operators must meet the following conditions at a minimum. (1)As a pre-condition to receiving a building permit, a construction site operator must prepare and submit a stormwater pollution prevention plan (SWP3).

Full Breakdown

Before a building or site development permit is issued, construction site operators must prepare and submit a stormwater pollution prevention plan (SWP3) that details erosion and sediment controls, keeps soil and sediment on-site, and follows a maintenance and inspection schedule. Sites under one acre still must control soil and sediment from leaving the property and clean up daily; sites of five or more acres require a copy of the TCEQ notice of intent. Sediment basins are required where feasible for drainage areas of ten or more disturbed acres. The city's Stormwater Program, at 415 W University Drive, administers the rule.

Violations & Fines

Unreasonable denial of city inspection access or an illicit MS4 connection is an offense; general code violations carry fines up to $500 per day, with each day a separate offense.

Frequently Asked Questions

Do all Edinburg construction sites need a stormwater plan?
Yes. Any project needing a building or site development permit, or involving excavation, fill, or grading, must submit an SWP3 first, per Sec. 98.30(C).
How often must sediment be removed from traps?
No later than when a sediment trap or pond's design capacity is reduced by 50 percent, per Sec. 98.30(G)(3)(b).

Sources & Official References

Other rules in Edinburg

All Edinburg rules

Texas rules heatmap·Compare Edinburg to another location·View the Texas environmental rules overview

Get notified when Erosion Control in Edinburg, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Hidalgo County handle erosion control.

Pharr, TX
Light Restrictions
Mission, TX
Some Restrictions