Monroe Township (Gloucester County), NJ Environmental Rules: Erosion Control (2026)
Key Facts
- Applies to
- All site plans and major subdivisions
- Building permit
- Withheld until the State Act is satisfied or waived
- Plan approval
- Soil Conservation District certification or proof of waiver
- Submit to
- Approving authority and Construction Official
- Closeout
- District acceptance before guaranty release or certificate of occupancy
- Topsoil cover
- At least five inches of spread cover (§ 175-117.1F)
Summary
In Monroe Township, Gloucester County, § 175-136 requires every site plan and major subdivision to include a soil erosion and sediment control program phased with the development schedule. No building permit issues until the State Soil Erosion and Sediment Control Act is satisfied or waived, and the Soil Conservation District must accept the measures before a certificate of occupancy or any release of performance guaranties.
All site plans and major subdivisions shall incorporate soil erosion and sediment control programs phased according to the scheduled progress of the development, including anticipated starting and completion dates. ... A. No building permit shall be issued for any development application until all provisions of the State of New Jersey Soil Erosion and Sediment Control Act, P.L. 1975, c. 251, have been satisfied or waived.[1] ... B. Development applicants shall submit to the approving authority and Construction Official copies and documentation of the approval and certification of the Soil Erosion and Sediment Control Plan by the Soil Conservation District, or proof of waiver of the same. C. Prior to the release of any performance guaranties, or the issuance of a certificate of occupancy in the case of a site plan, evidence of the acceptance of all soil erosion control measures by the Soil Conservation District must be submitted to the Construction Official and Township Engineer.
Full Breakdown
Section 175-136 of the Monroe Township Code applies to all site plans and major subdivisions in the Township, and each has to incorporate soil erosion and sediment control programs phased according to the scheduled progress of the development, including anticipated starting and completion dates. The stated purpose is to control soil erosion, sediment damages and related environmental damage by requiring adequate provisions for surface water retention and drainage and for the protection of exposed soil surfaces.
Three conditions follow. Under Subsection A, no building permit is issued for any development application until all provisions of the State of New Jersey Soil Erosion and Sediment Control Act, P.L. 1975, c. 251, have been satisfied or waived. Under Subsection B, applicants submit to the approving authority and the Construction Official copies and documentation of the Soil Conservation District's approval and certification of the Soil Erosion and Sediment Control Plan, or proof of a waiver. Under Subsection C, before any performance guaranty is released, or before a certificate of occupancy issues in the case of a site plan, evidence that the Soil Conservation District accepted all soil erosion control measures has to go to the Construction Official and the Township Engineer.
Related sections tighten the field rules. Section 175-137 requires excavation and grading to follow the Soil Conservation District approved plan, prohibits excavation of soil other than what approved structures and supporting facilities such as streets, driveways and parking areas require (except authorized resource extraction under § 175-130), and requires regraded areas to be stabilized by seeding and planting. Section 175-117.1F, the residential lot grading standards, requires topsoil moved during construction to be redistributed with at least five inches of spread cover on seeded and planted areas and stabilized by seeding or planting, sets slopes no steeper than three horizontal to one vertical, and bars grading within five feet of a property line unless needed to direct drainage into acceptable facilities. Subsection E of that section withholds a certificate of occupancy until the Engineer approves an as-built final survey. Section 175-140 on stormwater names stream channel erosion and sediment transport as consequences of poorly managed runoff.
Violations & Fines
Section 175-136 prints no fine of its own; the enforcement is the permit gate. Without Soil Conservation District certification or a waiver, no building permit issues. Release of performance guaranties, and a certificate of occupancy for a site plan, both require evidence that the District accepted the erosion control measures. Unauthorized soil excavation is separately prohibited under § 175-137.
Frequently Asked Questions
Does a builder in Monroe Township need Soil Conservation District approval?
When does the erosion control have to be accepted?
Can soil be hauled off a development site in Monroe Township?
What does the code require for topsoil and slopes on residential lots?
Sources & Official References
Other rules in Monroe Township (Gloucester County)
Compare Monroe Township (Gloucester County) to another location·View the New Jersey environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.