Skip to main content
CityRuleLookup

Palm Desert, CA Environmental Rules: Erosion Control (2026)

Some Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified October 2026

Key Facts

Core rule
Palm Desert Municipal Code § 27.12.065, Erosion control
Slope irrigation
Designed automatic system approved by the city engineer
Plant establishment
Minimum ninety days before calling for final approval
Construction sites
Must comply with § 27.12.065 under § 24.20.100
Enforcement
Stop work notice from city engineer or building official
Appeal
Written appeal to city council within fifteen calendar days

Summary

In the City of Palm Desert, grading under a city permit carries erosion duties. A slope planted for erosion control needs a designed automatic irrigation system approved by the city engineer and a minimum ninety-day plant establishment period before final approval. The owner must keep drainage structures and protective devices in repair, and every construction site must follow Section 27.12.065.

§ 27.12.065. Erosion control. A. Where slopes are planted for erosion control, the slope shall be watered by a designed automatic irrigation system approved by the city engineer. The irrigation system and landscaping shall have their own plans and specifications. Landscaping shall have a minimum ninety-day plant establishment period prior to calling for final approval. B. The manner(s) of erosion control shall be specifically addressed in the report required by Section 7006 of the Uniform Building Code. C. The owner of any property on which grading has been performed pursuant to a permit issued under the provisions of this code, or any other person or agent in control of such property, shall maintain in good condition and repair all drainage structures and other protective devices and burrowing rodent control when shown on the grading plans filed with the application for grading permit and approved as a condition precedent to the issuance of such permit.

Full Breakdown

Palm Desert regulates erosion through its grading title, Title 27, and its stormwater chapter, Chapter 24.20. Section 27.12.065 is the core rule. Where a slope is planted for erosion control, the slope must be watered by a designed automatic irrigation system approved by the city engineer, and the irrigation system and the landscaping each need their own plans and specifications. Landscaping must complete a minimum ninety-day plant establishment period before anyone calls for final approval. The manner of erosion control has to be addressed in the report required by Section 7006 of the Uniform Building Code. After grading is done, the owner of the property, or any other person or agent in control of it, must maintain in good condition and repair the drainage structures, other protective devices and burrowing rodent control shown on the grading plans filed with the grading permit application.

Other sections add to that rule. Section 27.12.140 requires the permittee to take the steps reasonably necessary to prevent a nuisance, and it names spillage, dust, erosion and noise control. Section 27.12.059 requires drainage devices to convey drainage to an established water course, channel, storm drain or public street and to be designed to prevent erosion. Section 24.20.100 ties any person performing construction work in the City of Palm Desert to Section 27.12.065, and Section 24.20.120 requires a discharger associated with construction activity to comply with the construction activity stormwater general permit, with proof of compliance required in a form acceptable to the director before the city issues grading, building or occupancy permits. Section 8.70.090 separately bars maintaining or grading land so as to cause erosion, subsidence or surface water drainage problems that endanger public health or safety.

Permits control the timing. Under Section 27.12.180, no building permit issues until the city engineer has approved the grading plans and a current grading permit has been issued, with an exception for minor construction as defined by the city engineer. Section 27.12.200 holds the final inspection approval and certificate of occupancy until the city engineer gives final approval of the finished grading.

Violations & Fines

Land alteration commenced or done contrary to Title 27 is unlawful and a public nuisance under Section 27.36.020. The city engineer or city building official can issue a stop work notice, and on order of the city council the city attorney starts proceedings to abate, remove or enjoin the nuisance. Failing to obtain a required permit is prima facie evidence of the nuisance. The building official can suspend a building permit until a land alteration permit is issued (Section 27.12.110). An applicant can appeal a city engineer decision in writing to the city council within fifteen calendar days (Section 27.36.010).

Frequently Asked Questions

Who approves the irrigation on a planted erosion-control slope in Palm Desert?
The city engineer. Section 27.12.065(A) requires a slope planted for erosion control to be watered by a designed automatic irrigation system approved by the city engineer. The irrigation system and the landscaping each carry their own plans and specifications, and the landscaping needs a minimum ninety-day plant establishment period before anyone calls for final approval.
Does a construction site in the City of Palm Desert need a stormwater permit too?
Section 24.20.120 requires any discharger associated with construction activity to comply with the construction activity stormwater general permit. The director can require proof of compliance in an acceptable form before the city issues grading, building or occupancy permits. Section 24.20.100 separately binds any person performing construction work in the city to that chapter and to Section 27.12.065.
Who maintains drainage structures after grading is finished?
The property owner, or any other person or agent in control of the property, under Section 27.12.065(C). The duty covers drainage structures, other protective devices and burrowing rodent control, when those items are shown on the grading plans filed with the grading permit application and approved as a condition of the permit.
What happens if grading starts without a permit in Palm Desert?
Land alteration contrary to Title 27 is unlawful and a public nuisance under Section 27.36.020. The city engineer or city building official can issue a stop work notice, and failure to obtain a required permit is prima facie evidence that a nuisance exists. The building official can also suspend any building permit until a land alteration permit is issued under Section 27.12.110.

Sources & Official References

Other rules in Palm Desert

All Palm Desert rules

California rules heatmap·Compare Palm Desert to another location·View the California environmental rules overview

Get notified when Erosion Control in Palm Desert, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Riverside County handle erosion control.

Corona, CA
Some Restrictions
Menifee, CA
Some Restrictions
Moreno Valley, CA
Some Restrictions
Murrieta, CA
Significant Restrictions
Palm Springs, CA
Some Restrictions
Riverside, CA
Some Restrictions
Temecula, CA
Some Restrictions