Pearland, TX Environmental Rules: Erosion Control (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Governing section
Code § 30-146, Ch. 30, Art. VI
Trigger threshold
1+ acre of land disturbance
Small-site rule
Under 1 acre: city-approved erosion plan on site
Permit types covered
Site work, building, grading, major construction
Exempt
Single-family additions; necessary facility repairs
Adopting ordinance
Ord. No. 1570, 12-17-18

Summary

Pearland bans land-disturbing construction activity without a city permit and requires an approved erosion and sediment control plan for any site disturbing an acre or more. The city engineer reviews stormwater pollution prevention plans and can stop work or revoke a permit for violations.

It shall be unlawful for a person to conduct any land disturbing activity in the absence of a city issued permit authorizing such work. Such permits include, without limitation, site work permit, building permits, grading permits, and major construction improvement permits... To prevent the adverse impacts of storm water runoff, the performance standards required by this article shall be applied at new development sites where any construction activity disturbs one (1) or more acres of land.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: Code of Ordinances: Supplement 28).

Full Breakdown

Sec. 30-146 of the General Code applies to all subdivision and site plan applications and to any construction activity that disturbs the topsoil, and it requires performance standards be applied at new development sites where construction disturbs one or more acres of land. Sec. 30-146(c) makes it unlawful to conduct any land-disturbing activity without a city-issued permit, which can include a site work permit, building permit, grading permit, or major construction improvement permit. Large construction activity operators must maintain an NPDES or TPDES general permit and submit to the city engineer a copy of the notice of intent filed with EPA or TCEQ, a site plan showing erosion control measure locations, and a construction site storm water pollution prevention plan (SWPPP) before obtaining a city construction permit.

Smaller sites disturbing less than one acre must instead implement and maintain a copy of a city-approved erosion control plan at the site. Design requirements under Sec. 30-146(i) mandate that all grading plans comply with the Unified Development Code and the city's Engineering Design Criteria Manual, and that erosion and sediment control practices be adequate to prevent sediment from leaving the site; clearing techniques must retain natural vegetation and drainage patterns where practicable, using ditches, berms, or other best management practices, and protecting slopes with erosion control blankets or turf reinforcement mats.

The rule exempts additions or modifications to an existing single-family structure and repairs to a stormwater treatment facility the city deems necessary. The city engineer reviews each SWPPP and may approve it, approve it with conditions, or disapprove it and require a revised submission under Sec. 30-146(d).

Violations & Fines

It is an offense under Sec. 30-146(f) and (h) for storm water runoff associated with construction activity to discharge without a required NPDES or TPDES permit, or for an operator to discharge without first submitting the notice of intent to the city. Under Sec. 30-146(l), the city engineer may issue a stop work order or suspend or revoke the permit when there is reasonable cause the permittee violated permit terms or created a condition materially adverse to public health, safety, or welfare, in addition to any other penalty under the article.

Frequently Asked Questions

Do I need a permit to clear and grade land in Pearland?
Yes. Sec. 30-146(c) makes it unlawful to conduct any land-disturbing activity without a city-issued permit such as a site work, building, grading, or major construction improvement permit, and compliance is required before the city issues that permit.
When does Pearland require a full erosion control plan versus a simpler one?
Sites disturbing one acre or more must maintain an NPDES or TPDES general permit with a full SWPPP submitted to the city engineer under Sec. 30-146(c)(2). Sites disturbing less than one acre only need to implement and keep a city-approved erosion control plan on site under Sec. 30-146(c)(4).
Is a single-family home addition subject to Pearland's erosion control rule?
No. Sec. 30-146(b)(4)(a) exempts an addition or modification to an existing single-family structure from this section, along with repairs to a storm water treatment facility that the city deems necessary.

Sources & Official References

Other rules in Pearland

All Pearland rules

Texas rules heatmap·Compare Pearland to another location·View the Texas environmental rules overview

Get notified when Erosion Control in Pearland, TX changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.