Skip to main content
CityRuleLookup

Petaluma, CA Environmental Rules: Erosion Control (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified September 2026

Key Facts

Permit required for
Any grading, excavation, fill, clearing
Issuing department
Public works department
Rainy season
October 1 to April 15
Small-job exemption
≤150 cu yd, ≤4 ft deep
Work hours near homes
6am-8pm weekdays, 8am-5pm Sat
Enforcement
Public nuisance abatement action

Summary

Petaluma's Grading Ordinance bars any grading, excavation or fill work without a public works department permit and requires erosion and sediment control measures, including a standby crew during the rainy season, on active job sites. Violations are treated as a public nuisance the city attorney can sue to abate.

17.31.040 Actions prohibited. It shall be unlawful for any person to: A. Perform any work within the scope of this chapter without first having obtained a permit from the public works department pursuant to this chapter, and/or, from the building inspection department, where required by Chapter 70 of the Uniform Building Code. ... C. Grade in such a manner so as to: 1. Cause erosion or sedimentation on other property or on public streets, 2. Obstruct or otherwise interfere with drainage, or deposit sediment in natural or artificial drainage facilities, or 3. Construct or alter drainage facilities or alter drainage courses without first obtaining a permit pursuant to chapter 17.31.060. ... 17.31.240 Erosion control. ... B. The faces of cut and fill slopes must be protected against damage by erosion and the methods utilized for such protection must offer effective erosion control prior to the beginning of, as well as during, the rainy season. ... H. Sediment control facilities must be constructed and in working order prior to the beginning of the rainy season and must prevent sediment from being transported from the site.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 2931 NCS, passed July 6, 2026).

Full Breakdown

31, the 'Grading Ordinance of the city of Petaluma,' regulates grading on public and private property to control erosion and sedimentation, protect water quality and reduce stormwater pollutants. 060 permit. 070 exempts small jobs, such as excavations of 150 cubic yards or less at four feet deep or shallower, and vegetation clearing on slopes of 20 percent or less limited to one acre. 030), slopes steeper than 3:1 or higher than ten feet need temporary stabilization such as jute matting, sediment control facilities must be working before the rainy season begins, and the permittee must keep a standby emergency crew and stockpiled erosion-control materials available throughout the rainy season and inspect all devices after every rainfall. m. Saturdays.

Violations & Fines

Section 17.31.320 declares any grading, excavation or work performed contrary to Chapter 17.31 unlawful and a public nuisance; on order of the city council, the city attorney must commence an action to abate, remove and enjoin the violation, and the city can apply to any court with jurisdiction to restrain continued noncompliance, in addition to other penalties available under the Municipal Code.

Frequently Asked Questions

Do I need a permit to grade or excavate my Petaluma property?
Yes, in almost all cases. Section 17.31.060 requires a public works department permit for excavation, moving or depositing earth materials, and clearing vegetation. Section 17.31.070 exempts small jobs, such as excavation or fill of 150 cubic yards or less at four feet deep or shallower, and clearing an acre or less on gentle slopes.
What erosion control measures does Petaluma require during construction?
Section 17.31.240 requires cut and fill slopes to be protected before and through the rainy season (October 1 to April 15), temporary stabilization like jute matting on steep or tall slopes, working sediment control facilities before the rains start, a standby emergency crew, stockpiled repair materials, and inspection of all devices after every rainfall.
What happens if grading work in Petaluma violates the erosion control ordinance?
Section 17.31.320 makes noncompliant grading a public nuisance; the city attorney can sue to abate, remove and enjoin the work on the city council's order, on top of any other Municipal Code penalty. Work can also be halted outright by the director of public works during inclement weather under Section 17.31.250.

Sources & Official References

Other rules in Petaluma

All Petaluma rules

California rules heatmap·Compare Petaluma to another location·View the California environmental rules overview

Get notified when Erosion Control in Petaluma, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Erosion Control in Nearby Cities

How other cities in Sonoma County handle erosion control.

Santa Rosa, CA
Some Restrictions