Key Facts

Standard freeboard
12 inches above base flood elevation
Zero-net-fill area freeboard
2 feet minimum
Applies to
New/substantially improved FP-C zone buildings
Also covers
HVAC, electrical and plumbing equipment
Certification required
Registered engineer or licensed surveyor
Manufactured homes
Same 12-inch rule under §6.070(D)(1)

Summary

Petaluma requires new and substantially improved buildings in its floodplain to elevate the lowest floor at least 12 inches above the base flood elevation shown on FEMA's flood insurance rate map, with a stricter two-foot minimum in the Redwood Business Park II zero-net-fill area along the river.

New construction and substantial improvement/substantial damage of any residential structure permitted in FP-C (floodplain-combining) zones shall have the lowest habitable floor, including basement, and all machinery and equipment including but not limited to electrical, heating, ductwork, ventilation, plumbing, and air conditioning, elevated at least 12 inches above the level of the base flood elevation or depth number specified on the FIRM (flood insurance rate map), whichever applies to the area, unless otherwise restricted in subsection (D)(2) of this section. ... In this area, clearance above base 100 year flood elevation for finished floors shall be a minimum of two feet, and zero net fill as defined shall apply to any proposed development activity.

View official code

Official source re-checked September 8, 2026: no newer edition of the code had been published (publisher’s edition: current through Ordinance 2931 NCS, passed July 6, 2026).

Full Breakdown

070(D) sets Petaluma's freeboard standard: new construction and substantial improvement or substantial-damage repair of any residential structure in the FP-C (Flood Plain-Combining) zone must have its lowest habitable floor, including any basement, elevated at least 12 inches above the base flood elevation or the depth number shown on the Flood Insurance Rate Map (FIRM), whichever applies. That 12-inch freeboard also covers all mechanical, electrical, heating, ventilation, plumbing and air-conditioning equipment, which must sit above the same line. 080(C). 070(D)(1), measured to the lowest floor of each home on reinforced piers or an equivalent foundation, and any new manufactured home park, or an existing park expanding 10 percent or more, must include a written emergency evacuation plan.

070(D)(2), finished floor clearance above the 100-year base flood elevation must be a minimum of two feet, not 12 inches, and any fill placed on a project site there must be offset by removing an equivalent amount of material elsewhere on the parcel or nearby, to the satisfaction of the City Engineer and the Sonoma County Water Agency. 070(E), or may instead be engineered watertight and floodproofed below the base flood level, certified by a registered engineer or architect.

Violations & Fines

Occupying or completing a residential structure in the FP-C zone without the required 12-inch (or two-foot, in the zero-net-fill area) freeboard, or without the post-construction elevation certification a registered engineer or surveyor must file under §6.070(D) and §6.080(C), is a code violation; §6.030(NN) presumes noncompliance whenever that certificate is missing until it is supplied, and enforcement runs through the misdemeanor provision in §6.070(A).

Frequently Asked Questions

How high above base flood elevation must a Petaluma home be built?
IZO §6.070(D) requires the lowest habitable floor, including any basement, of a new or substantially improved residential structure in the FP-C zone to sit at least 12 inches above the base flood elevation or the FIRM depth number, whichever applies, with mechanical and utility equipment held to the same line.
Is the freeboard requirement different near Redwood Business Park II?
Yes. Under the zero-net-fill policy in §6.070(D)(2), the area along the Petaluma River upstream of the Payran Street Bridge, including Redwood Business Park II, requires two feet of clearance above the 100-year base flood elevation, not 12 inches, and any fill must be offset by removing an equal volume of material.
Who certifies that a Petaluma building meets the elevation requirement?
A registered professional engineer or licensed land surveyor must certify the as-built lowest-floor elevation once construction is complete, and that certification is filed with the Floodplain Administrator and kept on record by the Community Development Department under IZO §6.080(C).
Does the 12-inch rule apply to manufactured homes too?
Yes. IZO §6.070(D)(1) applies the same 12-inch freeboard to manufactured homes in floodplain parks, measured to the lowest floor on reinforced piers or an equivalent foundation, and bars any new manufactured home from floodway (FW) land entirely.

Sources & Official References

Other rules in Petaluma

All Petaluma rules

California rules heatmap·Compare Petaluma to another location·View the California environmental rules overview

Get notified when Flood Elevation Requirements in Petaluma, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.

Flood Elevation Requirements in Nearby Cities

How other cities in Sonoma County handle flood elevation requirements.

Santa Rosa, CA
Some Restrictions