Roseville, CA Environmental Rules: Erosion Control (2026)

Significant Restrictions
Compiled from the official code textEditor Martyn O'NeillLast verified August 2026

Key Facts

SWPPP trigger
Construction disturbing 1 acre or more
Governing section
RMC Sec. 14.20.290(C)
Enforcement tool
Stop work order, Sec. 14.20.480
City guidance doc
Construction Activities BMP Guidance Manual
Penalty type
Infraction or misdemeanor, city attorney's choice

Summary

Roseville requires any construction project subject to a State Water Resources Control Board stormwater pollution prevention plan (SWPPP) to follow that plan at all times, and the city can order the crew to correct any failure or stop work outright. City Code Section 14.20.290(C) folds the state SWPPP obligation into the city's own stormwater enforcement chapter.

Any landowner or person responsible for construction activities that is required by the State Water Resources Control Board to prepare a stormwater pollution prevention plan (SWPPP) must, at a minimum, adhere to the reviewed SWPPP. If the reviewed SWPPP, or any element thereof, is not fully implemented or is not functioning as needed to protect the waters of the United States, the responsible party will be required to immediately correct insufficiencies or will be subject to the enforcement procedures set forth in this chapter.

Full Breakdown

290(C) requires anyone responsible for that construction to adhere, at a minimum, to the SWPPP the state reviewed. If the SWPPP is not fully implemented or is not functioning to protect waters of the United States, the responsible party must immediately correct the shortfall or face the chapter's enforcement procedures. Roseville backs this with its own Stormwater Quality Best Management Practices Guidance Manual for Construction Activities, published on the city's website and built to be consistent with the California Storm Water Quality Association's BMP Handbook.

170, reviewed and accepted by the city engineer before a permit to construct issues, detailing how erosion, sediment and other pollutants generated on site will be controlled, managed and treated, including low-impact development and hydromodification measures. 160.

Violations & Fines

Section 14.20.480 lets the city engineer or an enforcement officer stop work by written notice to anyone doing work contrary to the chapter, and that work must halt until the city engineer authorizes it to resume. Failing to adhere to a reviewed SWPPP or to correct a deficiency exposes the responsible party to Section 14.20.410's general violation provisions, chargeable as an infraction or misdemeanor at the city attorney's discretion, and to a cease-and-desist order under Section 14.20.430 requiring cleanup within 72 hours of notification.

Frequently Asked Questions

Does Roseville require a stormwater pollution prevention plan for construction?
Construction disturbing one acre or more triggers the State Water Resources Control Board's NPDES construction permit and its SWPPP requirement, and Section 14.20.290(C) requires the responsible party to adhere to that reviewed SWPPP at all times as part of the city's own stormwater chapter.
Can Roseville stop construction work over a stormwater violation?
Yes. Section 14.20.480 authorizes the city engineer or an enforcement officer to order work stopped by written notice whenever it is being done contrary to Chapter 14.20, and the work must halt until the city engineer authorizes it to proceed again.
What happens if a construction site's erosion controls fail in Roseville?
Section 14.20.290(C) requires the responsible party to immediately correct any SWPPP element that is not fully implemented or functioning to protect water quality, or face the chapter's enforcement procedures, including a cease-and-desist order under Section 14.20.430 requiring cleanup within 72 hours of notification.

Sources & Official References

Other rules in Roseville

All Roseville rules

California rules heatmap·Compare Roseville to another location·View the California environmental rules overview

Get notified when Erosion Control in Roseville, CA changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.