Royal Oak Township, MI Environmental Rules: Erosion Control (2026)
Key Facts
- Governing standard
- § 32-80(11), site plan approval criterion on soil erosion and sedimentation
- When measures apply
- During and upon completion of construction
- Benchmark
- Current county and township standards
- Grading permit trigger
- Grading, excavating, filling, stockpiling, or other alteration (§ 32-627)
- Grading plan preparer
- Registered land surveyor or civil engineer
- Final grading deadline
- No later than six months after certificate of occupancy
- Penalty
- Misdemeanor: fine up to $500.00, up to 90 days, each day separate
Summary
Site plans in Royal Oak Township, Michigan must include measures that prevent soil erosion and sedimentation during and upon completion of construction, judged against current county and township standards. Section 32-80 of the Charter Township of Royal Oak code sets the test, and the building official or township engineer reviews grading and drainage plans.
The following criteria shall be used as a basis upon which site plans will be reviewed and approved: ... (10) Drainage. Appropriate measures shall be taken to ensure that the removal or drainage of surface water will not adversely affect adjoining properties or the capacity of the public drainage system. Provisions shall be made for a feasible storm drainage system, the construction of stormwater collection, storage and transportation facilities, and the prevention of erosion. ... (11) Soil erosion and sedimentation. The proposed development shall include measures to prevent soil erosion and sedimentation during and upon completion of construction, in accordance with current county and township standards.
Full Breakdown
In the Charter Township of Royal Oak, erosion control is built into site plan approval rather than written as a stand-alone ordinance. Section 32-80 lists the criteria the Township uses to review and approve site plans. Criterion (11) requires the proposed development to include measures to prevent soil erosion and sedimentation during and upon completion of construction, in accordance with current county and township standards. The required site plan contents in § 32-79 separately list soil erosion and sedimentation control measures alongside site grading, drainage patterns and proposed contours, so the measures have to be drawn on the plan before review starts.
Criterion (10) on drainage adds that provisions must be made for a feasible storm drainage system and the prevention of erosion, and that grading and drainage plans are subject to review by the building official or the township engineer.
Earth moving has its own permit trigger. Under § 32-627(a)(2), a permit is required wherever grading, excavating, filling, stockpiling, or other alteration to the land is proposed, with an exception for minor alterations that do not affect the storm drainage pattern. The applicant first submits a grading plan to the building official, prepared by a registered land surveyor or civil engineer. Under § 32-627(c)(2), newly established grades cannot increase the runoff of surface water onto adjacent properties except through established drainage courses. Rough grading must be finished before final inspection and issuance of a certificate of occupancy, and final grading must be completed no later than six months after the certificate of occupancy is issued.
Section 32-629 adds two related rules. Filling with soil, sand, clay, gravel or similar earthen material requires plan review and a permit from the building official first. Removing topsoil, sand, gravel or similar material from any site in the township requires the building official's approval, and a permit is issued only on a finding that the removal will not cause stagnant water to collect or leave the surface of the land in an unstable condition.
Violations & Fines
A violation of Chapter 32 is a misdemeanor under § 32-262, punishable by a fine not exceeding $500.00 or imprisonment not exceeding 90 days, or both, for each offense, and each day a violation continues is a separate offense. Owners, contractors and anyone who participates in a violation can each be charged, and prosecution costs are assessed against the violator. Under § 32-260 a use carried on in violation is a nuisance per se, and under § 32-263 the building official can seek relief in circuit court.
Frequently Asked Questions
Does a construction project in Royal Oak Township need erosion control measures?
When is a grading permit required in the Charter Township of Royal Oak?
Who reviews grading and drainage plans?
Can I move topsoil off my lot in Royal Oak Township?
What is the penalty for violating the zoning chapter?
Sources & Official References
Other rules in Royal Oak Township
Compare Royal Oak Township to another location·View the Michigan environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.
Erosion Control in Nearby Cities
How other cities in Oakland County handle erosion control.