Key Facts

Trigger
Any land development activity
Required plan
Stormwater Pollution Prevention Plan (SWPPP)
Exempt land disturbance
Under 1 acre, agricultural use
Per-day fine
Up to $250, each day separate
Enforcement tool
Stop-work order under § 148-18
Adopted
L.L. No. 5-2007

Summary

Schenectady bars starting any land development activity without an approved stormwater pollution prevention plan (SWPPP) covering erosion and sediment control, reviewed by the responsible board or the Stormwater Management Officer; violators face a stop-work order and fines up to $250 per day under Chapter 148, Article I.

Except as otherwise provided herein, no person shall commence or perform any land development activity as defined in § 148-5 herein without the review and approval of a stormwater pollution prevention plan (SWPPP) by the responsible board and/or the Stormwater Management Officer.

View official code

Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: rev 4990798; v11 updated 2026-04-13; through 04-13-2026).

Full Breakdown

Chapter 148, Article I, adopted in 2007, requires review and approval of a stormwater pollution prevention plan (SWPPP) before any land development activity begins, per § 148-4A, except for a defined list of exempt activities in § 148-4D: emergency work, agricultural operations disturbing less than one acre, routine maintenance of drainage facilities, mining, septic system replacement on an existing dwelling, ordinary lawn care and home gardening, and forestry conducted under a management plan. Redevelopment projects must follow Chapter 9 of the New York State Stormwater Management Design Manual and are encouraged under § 148-4C to use practices like rain gardens, pervious pavers and green roofs to reduce impacts where full compliance isn't achievable on a constrained urban site.

Applicants must also secure any other state, federal or local permits, and where site plan or subdivision approval is required, the responsible board integrates the SWPPP review into that process. The Stormwater Management Officer administers the article under § 148-10 for plan review and § 148-13 for construction inspection, and requires a project completion inspection before releasing any performance guarantee posted under § 148-16. If land development proceeds out of compliance, § 148-18 lets the Officer issue a written notice of violation describing the remedial measures and a compliance deadline, and issue a stop-work order halting all activity except work that addresses the violation. The Building Inspector may also withhold a certificate of occupancy until the site is brought into compliance.

Violations & Fines

Section 148-18D makes a violation of the erosion and sediment control article a misdemeanor, with each day a violation continues counted as a separate offense, punishable by a fine of up to $250 per offense. A violator must also pay to restore the site, and noncompliance that also breaches the Clean Water Act or the state Environmental Conservation Law can add substantial separate criminal, civil or administrative penalties.

Frequently Asked Questions

Do I need a permit before grading or clearing land in Schenectady?
Yes, unless an exemption applies. Section 148-4A requires review and approval of a stormwater pollution prevention plan (SWPPP) by the responsible board or the Stormwater Management Officer before any land development activity begins. Small residential projects like normal lawn care, home gardening and agricultural work disturbing under an acre are exempt under § 148-4D.
What happens if construction erosion controls aren't followed in Schenectady?
The Stormwater Management Officer can issue a written notice of violation under § 148-18 specifying the remediation needed and a deadline, and can issue a stop-work order halting all activity except the fix. The Building Inspector can also withhold the certificate of occupancy until the site complies.
What's the fine for an erosion-control violation in Schenectady?
Section 148-18D sets a fine of up to $250 per offense, and treats each day the violation continues as a separate offense, on top of requiring the violator to pay for site restoration. Violations that also breach the federal Clean Water Act can trigger additional state or federal penalties.

Sources & Official References

Other rules in Schenectady

All Schenectady rules

New York rules heatmap·Compare Schenectady to another location·View the New York environmental rules overview

Get notified when Erosion Control in Schenectady, NY changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.