St. Peters, MO Environmental Rules: Erosion Control (2026)
Key Facts
- Permit required
- Grading permit from the City Engineer
- Plan requirement
- Site erosion and siltation control plan
- Basin trigger
- Grading over 20,000 square feet
- Standard referenced
- City Erosion and Sediment Mgmt Practices
- Appeals
- Board of Adjustment, Section 530.100
Summary
In the City of St. Peters, Missouri, anyone seeking a grading permit from the City Engineer must submit a site erosion and siltation control plan under Section 530.020(A)(6). Grading projects that disturb more than twenty thousand square feet must go further under Section 530.050(B)(7)(c), adding sediment or debris basins, silt traps, or staked straw bales to the plan.
6. Details of site erosion and siltation control, including siltation basins and re-vegetation, following the practices outlined in the most current edition of the "City of St. Peters, Missouri Standards for Erosion and Sediment Management Practices". ... ... c. Sediment and erosion control plans for sites that exceed twenty thousand (20,000) square feet of grading shall provide for sediment or debris basins, silt traps or filters, staked straw bales or other approved measures, as set forth in the "City of St. Peters, Missouri Standards for Erosion and Sediment Management Practices", to remove sediment from runoff waters. The grading, sediment and erosion control plans and maintenance schedule are to be approved by the City Engineer or his/her designee.
Full Breakdown
Chapter 530, Grading, requires a permit from the City Engineer or the Engineer's designee before most excavation or fill activity begins on a site in the City of St. Peters, Missouri. The permit application itself, under Section 530.020(A), must include details of site erosion and siltation control, including siltation basins and re-vegetation, following the City's own "Standards for Erosion and Sediment Management Practices," along with an estimated schedule showing the grading start date, the date the erosion and siltation control goes in, dates for re-vegetation, and the completion date for grading operations.
Section 530.050 then sets the substantive standards that the permit is conditioned on. Under Subsection (B)(7)(c), any site where grading exceeds twenty thousand square feet must include sediment or debris basins, silt traps or filters, staked straw bales, or other approved measures in its sediment and erosion control plan, and the City Engineer or the Engineer's designee must approve both the plan and its maintenance schedule. The same standards require temporary siltation control to stay in place until vegetative cover is established, and require development along natural watercourses to set structures and driveways back at least twenty-five feet from the top of the stream bank.
The City Engineer may promulgate additional erosion and sediment management rules consistent with these grading standards, and decisions can be appealed to the City's Board of Adjustment under Section 530.100.
Violations & Fines
Grading without an erosion and siltation control plan approved under Sections 530.020 and 530.050, or failing to maintain the required sediment controls, is an ordinance violation under Section 530.110 of the St. Peters Municipal Code. Each day the violation continues counts as a separate ordinance violation, and the City Engineer may also take corrective action at the violator's expense in addition to any court penalty.
Frequently Asked Questions
Does St. Peters require an erosion control plan for construction grading?
What triggers a stricter sediment control plan?
Who approves and enforces St. Peters grading and erosion rules?
What happens if a construction site violates the grading rules?
Sources & Official References
Other rules in St. Peters
Compare St. Peters to another location·View the Missouri environmental rules overview
See something wrong?