Key Facts

Permit required
Grading permit from the City Engineer
Plan requirement
Site erosion and siltation control plan
Basin trigger
Grading over 20,000 square feet
Standard referenced
City Erosion and Sediment Mgmt Practices
Appeals
Board of Adjustment, Section 530.100

Summary

In the City of St. Peters, Missouri, anyone seeking a grading permit from the City Engineer must submit a site erosion and siltation control plan under Section 530.020(A)(6). Grading projects that disturb more than twenty thousand square feet must go further under Section 530.050(B)(7)(c), adding sediment or debris basins, silt traps, or staked straw bales to the plan.

6. Details of site erosion and siltation control, including siltation basins and re-vegetation, following the practices outlined in the most current edition of the "City of St. Peters, Missouri Standards for Erosion and Sediment Management Practices". ... ... c. Sediment and erosion control plans for sites that exceed twenty thousand (20,000) square feet of grading shall provide for sediment or debris basins, silt traps or filters, staked straw bales or other approved measures, as set forth in the "City of St. Peters, Missouri Standards for Erosion and Sediment Management Practices", to remove sediment from runoff waters. The grading, sediment and erosion control plans and maintenance schedule are to be approved by the City Engineer or his/her designee.

Full Breakdown

Chapter 530, Grading, requires a permit from the City Engineer or the Engineer's designee before most excavation or fill activity begins on a site in the City of St. Peters, Missouri. The permit application itself, under Section 530.020(A), must include details of site erosion and siltation control, including siltation basins and re-vegetation, following the City's own "Standards for Erosion and Sediment Management Practices," along with an estimated schedule showing the grading start date, the date the erosion and siltation control goes in, dates for re-vegetation, and the completion date for grading operations.

Section 530.050 then sets the substantive standards that the permit is conditioned on. Under Subsection (B)(7)(c), any site where grading exceeds twenty thousand square feet must include sediment or debris basins, silt traps or filters, staked straw bales, or other approved measures in its sediment and erosion control plan, and the City Engineer or the Engineer's designee must approve both the plan and its maintenance schedule. The same standards require temporary siltation control to stay in place until vegetative cover is established, and require development along natural watercourses to set structures and driveways back at least twenty-five feet from the top of the stream bank.

The City Engineer may promulgate additional erosion and sediment management rules consistent with these grading standards, and decisions can be appealed to the City's Board of Adjustment under Section 530.100.

Violations & Fines

Grading without an erosion and siltation control plan approved under Sections 530.020 and 530.050, or failing to maintain the required sediment controls, is an ordinance violation under Section 530.110 of the St. Peters Municipal Code. Each day the violation continues counts as a separate ordinance violation, and the City Engineer may also take corrective action at the violator's expense in addition to any court penalty.

Frequently Asked Questions

Does St. Peters require an erosion control plan for construction grading?
Yes. Section 530.020(A)(6) of the St. Peters Municipal Code requires every grading permit application to include details of site erosion and siltation control, including siltation basins and re-vegetation, following the City's own Standards for Erosion and Sediment Management Practices.
What triggers a stricter sediment control plan?
Grading that exceeds twenty thousand square feet triggers the stricter standard in Section 530.050(B)(7)(c), which requires sediment or debris basins, silt traps or filters, or staked straw bales, all approved by the City Engineer along with a maintenance schedule for the site.
Who approves and enforces St. Peters grading and erosion rules?
The City Engineer or the Engineer's designee reviews and approves grading permits and erosion control plans under Chapter 530. Anyone who disagrees with the City Engineer's decision can appeal to the City's Board of Adjustment under Section 530.100.
What happens if a construction site violates the grading rules?
A grading or erosion control violation is an ordinance violation under Section 530.110, with each day the violation continues counted as a separate offense. The City Engineer can also have the condition corrected and bill the responsible party for the cost.

Sources & Official References

Other rules in St. Peters

All St. Peters rules

Compare St. Peters to another location·View the Missouri environmental rules overview

Get notified when Erosion Control in St. Peters, MO changes

We'll email you the moment we detect a change in the code. No spam, unsubscribe anytime.

We'll never sell or share your email. One-click unsubscribe in every email.

See something wrong?

Help us keep this page accurate. If you notice an error or outdated information, let us know.