Tazewell County, IL Environmental Rules: Erosion Control (2026)
Key Facts
- Governing chapter
- Ch. 151, Erosion Control
- Permit trigger
- 5,000+ sq ft disturbed or new home
- Standard plan fee
- $175
- Site specific plan fee
- $250
- Review time
- 2 or 5 working days
- Permit duration
- Up to 2 years
- Ground cover deadline
- Within 6 months of completion
Summary
Tazewell County requires an erosion and sediment control permit before disturbing land anywhere in the county's jurisdiction, covering new single- and two-family home construction and any project disturbing 5,000 square feet or more, with exceptions for normal farming and routine road or utility maintenance under §151.02.
(A) All projects within the boundaries and jurisdiction of the county. No land surface shall be disturbed unless an erosion and sediment control permit or an erosion sediment and stormwater control permit has first been issued for that project, except as follows: (1) Land disturbing activities which do not involve the construction of any new single- or two- family dwellings, and for which the disturbed area is less than 5,000 square feet; (2) Normal agricultural practices; or (3) Routine maintenance of roads and utility service lines.
Official source re-checked September 7, 2026: no newer edition of the code had been published (publisher’s edition: 2026 S-7: Supplement contains: Local legislation current through Ord. LU-21-12, passed 9-29-2021; and Res. LU-26-09, passed 7-29-2026).
Full Breakdown
Chapter 151, 'Erosion Control,' bars land disturbance countywide unless the owner first gets a permit. 02(A) states that 'no land surface shall be disturbed' unless an erosion and sediment control permit, or the larger erosion, sediment, and stormwater control permit, 'has first been issued for that project,' with three exceptions: disturbances under 5,000 square feet that don't involve a new single- or two-family dwelling, normal agricultural practices, and routine maintenance of roads and utility service lines. 05 sets the permit process for smaller projects: anyone building a new single- or two-family dwelling, or disturbing 5,000 square feet or more, must file a standard plan application (for slopes under 10% with no concentrated flow areas or water bodies on site) or a site specific plan (for steeper or wetter sites), paying a $175 fee for a standard plan or $250 for a site specific plan, though government and agricultural projects pay nothing.
The Erosion Control Administrator must approve or deny a standard plan within two working days and a site specific plan within five working days of a complete filing, or the application is deemed approved. 04 requires sediment control measures to be installed and functioning before any clearing, grading, or excavation begins, and to stay in place until permanent ground cover, such as pavement, sod, or seeded vegetation, is established, generally within three days of removing the sediment barriers. 05(E) further requires permanent ground cover on all disturbed areas within six months of project completion or occupancy, whichever comes first.
Violations & Fines
Disturbing land without the required permit, or failing to install or maintain the sediment control measures the permit calls for, is enforceable under §151.08 with a stop-work order carrying a $250 fee plus $20 for each day the violation continues, and §151.99 sets a separate fine of up to $500 per day for violating any term of the chapter.
Frequently Asked Questions
Do I need a permit to disturb less than 5,000 square feet of land?
How much does an erosion control permit cost in Tazewell County?
How long do I have to establish permanent ground cover after grading?
What happens if I start grading without a permit?
Sources & Official References
Other rules in Tazewell County
Compare Tazewell County to another location·View the Illinois environmental rules overview
See something wrong?
Help us keep this page accurate. If you notice an error or outdated information, let us know.